Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, S4, P4, S3, P7, P1, P5, S6, S7, P9, P8, P3, S2, S1, P2, 7161.house.L01, P6, S5 and S8, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Prior to the commencement of the development hereby approved samples of the materials to be used for the external walls and roofs shall be submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies CSEN3 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policy D1, G2 and H13 of the South Oxfordshire Local Plan 2011.
Prior to the commencement of the development hereby approved a detailed specification of any external ducts, flue pipes or means of external venting shall be submitted to and approved in writing by the Local Planning Authority and any such works shall be implemented in accordance with the approved details.
Reason: In the interests of the visual appearance of the development in accordance with Policies CSEN3 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies D1, G2 and H13 of the South Oxfordshire Local Plan 2011.
That the development hereby approved shall not commence until a detailed specification of the type, design and external finish of all windows and external doors has been submitted to and approved in writing by the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details.
Reason: In the interests of the visual appearance of the development in accordance with Policies CSEN3 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies D1, G2 and H13 of the South Oxfordshire Local Plan 2011.
That the development hereby approved shall be carried out in accordance with the details set out within the approved Flood Risk Assessment.
Reason: To prevent increased risk of flooding due to impedance of flood flows and reduction of flood storage capacity in accordance with the National Planning Policy Framework.
No development including site clearance stripping or demolition shall commence until either:
a) a bat licence issued by Natural England pursuant to the Regulation 53 of The Conservation of Habitats and Species Regulations 2017 authorising the specified activity to go ahead; or
b) proof of registration of the site for a bat low impact class licence, has been submitted to and agreed in writing by the Local Planning Authority.
Thereafter, the approved measures shall be carried out and retained in accordance with the approved details.
REASON: To protect the important species on the site, in accordance with Policy CSB1 of the South Oxfordshire Core Strategy 2027 and Policy C8 of the South Oxfordshire Local Plan 2011.