The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P17/S2354/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, D17-007-001, D17-007-002, D17-007-003-P3, D17-007-004-P4 and D17-007-005-P2, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Prior to any demolition and the commencement of the development a professional archaeological organisation acceptable to the Local Planning Authority shall prepare an Archaeological Written Scheme of Investigation, relating to the application site area, which shall be submitted to and approved in writing by the Local Planning Authority
Reason: To secure the protection of and proper provision for any archaeological remains in accordance with Policy CSEN3 of the South Oxfordshire Core Strategy 2027 and Policies CON11 and CON13 of the South Oxfordshire Local Plan 2011.
Following the approval of the Written Scheme of Investigation referred to in condition 3, and prior to any demolition on the site and the commencement of the development (other than in accordance with the agreed Written Scheme of Investigation), a staged programme of archaeological evaluation and mitigation shall be carried out by the commissioned archaeological organisation in accordance with the approved Written Scheme of Investigation. The programme of work shall include all processing, research and analysis necessary to produce an accessible and useable archive and a full report for publication which shall be submitted to the Local Planning Authority.
Reason: To enable an appropriate level of archaeological investigation of the area including excavation and recording, post excavation analysis and the publication of results in accordance with Policy CSEN3 of the South Oxfordshire Core Strategy 2027 and Policies CON11 and CON13 of the South Oxfordshire Local Plan 2011.