The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P18/S2440/DIS,
P18/S2881/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 585.02, 585.10, 585.12, 585.11, 585.06, 585.04, 585.08, 585.03, 585.07, 585.01, 585.09 and 585.05, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P18/S2440/DIS,
P18/S2881/DISPrior to the commencement of development, a schedule of external finish materials for areas of new construction shall be submitted to and approved in writing by the Local Planning Authority in writing.
Reason: In the interests of the visual appearance of the development in accordance with Policy CSEN3 of the South Oxfordshire Core Strategy 2027 and Policies CON 2 and CON 3 of the South Oxfordshire Local Plan 2011
Related application(s):
P18/S2440/DIS,
P18/S2881/DISA construction management plan detailing measures to be taken to protect nearby residents from noise and dust shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of any construction or demolition works. The hours of operation for such works shall be restricted to 8:00 am - 6.00 pm Monday to Friday and 8.00 am to 1.00 pm on a Saturday. No work shall take place on Sundays or Public Holidays without the prior written authority of the Local Planning Authority.
Reason: To safeguard the amenity of neighbouring residents in accordance with Policies G2 and EP2 of the South Oxfordshire Local Plan 2011.
Related application(s):
P18/S2440/DIS,
P18/S2881/DISThe applicant, or their agents or successors in title, shall be responsible for organising and implementing an archaeological watching brief, to be maintained during the period of construction/during any ground works taking place on the site. The watching brief shall be carried out by a professional archaeological organisation in accordance with a Written Scheme of Investigation that has first been approved in writing by the Local Planning Authority.
Reason: To safeguard the recording and inspection of matters of archaeological importance on site in accordance with the NPPF (2012) and in accordance with Policy CSEN3 of the South Oxfordshire Core Strategy 2027 and Policies CON11, CON13 and CON14 of the South Oxfordshire Local Plan 2011.
Following the approval of the Written Scheme of Investigation referred to in condition 5, no development shall commence on site without the appointed archaeologist being present. Once the watching brief has been completed its findings shall be reported to the Local Planning Authority, as agreed in the Written Scheme of Investigation ,including all processing, research and analysis necessary to produce an accessible and useable archive and a full report for publication.