Conditions / Refusal Reasons
Development shall not commence until details of the reserved matters [siting, appearance, landscaping, layout, scale and design] have been submitted to and approved in writing by the Local Planning Authority.
In the case of any reserved matter, application for approval must be made not later than the expiration of three years beginning with the date of the grant of outline planning permission.
Thereafter the development shall commence not later than whichever is the later of the following dates:
(a) the expiration of three years from the date of this permission; or
(b) the expiration of two years from the final approval of the reserved matters, or in the case of approval on different dates, the final approval of the last such matter to be approved.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
That, in so far as they relate to access to the site, the development hereby approved shall be carried out in accordance with the details shown on the following approved Site Location Plan dwg 6390/LOC1, and the indicative layout plan, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
The development hereby permitted shall not be occupied until foul drainage works have been carried out in accordance with details that have been first submitted to and approved in writing by the Local Planning Authority.
Reason: To prevent pollution in accordance with Policy EP1 of the South Oxfordshire Local Plan 2011.
The development hereby permitted shall not be occupied until surface water drainage works have been carried out in accordance with details that have been first submitted to and approved in writing by the Local Planning Authority.
Reason: To prevent pollution and flooding in accordance with Policies EP1, EP4 and EP6 of the South Oxfordshire Local Plan 2011.
Prior to the first use of the development hereby permitted the proposed means of access shown on Site Location Plan dwg 6390/LOC1 is to be formed and laid out and constructed strictly in accordance with the local highway authority's specifications and all ancillary works specified shall be undertaken.
Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
Prior to the first use of the development hereby approved a turning area and car parking spaces shall be provided within the curtilage of the site so that motor vehicles may enter, turn round and leave in a forward direction and vehicles may park off the highway. The turning area and parking spaces shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles in strict accordance with specification details to be submitted to and approved in writing by the Local Planning Authority prior to the first use of the development. The turning area and car parking spaces shall be retained unobstructed except for the parking and manoeuvring of motor vehicles at all times.
Reason: In the interests of highway safety and to ensure the provision of off-street car parking in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.
The off-site highway works shown on drawing no.6390/LOC1, or as otherwise agreed in writing with the Local Planning Authority shall be implemented in full before the first use of the development or in accordance with a programme of implementation agreed in writing with the Local Planning Authority.
Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
A Construction Traffic Management Plan (CTMP) shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The approved CTMP shall be implemented prior to any works being carried out on site, and shall be maintained throughout the course of the development.
Reason: In the interests of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, particularly at morning and afternoon peak traffic times and in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.