Description
Four dwellings (2 pairs of semi-detached) with access, parking and gardens.
Location
Land east of 206 Crowmarsh Hill Crowmarsh Gifford OX10 8BG
Grid Reference
462570/188848
Applicant
  J Dunsdon & M Pryce
c/o Agent JPPC
Agent
JPPC- Chartered Town Planners
Bagley Croft
Hinksey Hill
OXFORD
OX1 5BD
Case Officer
Katherine Pearce
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
Crowmarsh Parish Council
c/o Mrs S Rance
2 Home Farm
Crowmarsh Gifford
OX10 8EL
01 04 2017
20 02 2020
 
Countryside Officer(South Oxfordshire & Vale of White Horse)
01 04 2017
27 04 2017
 
Forestry Officer (South Oxfordshire District Council)
05 01 2018
25 01 2018
 
Highways Liaison Officer (Oxfordshire County Council)
01 04 2017
05 04 2017
 
Health & Housing - Contaminated Land
31 03 2017
31 03 2017
 
Whitebanks
Crowmarsh Hill
Crowmarsh Gifford
Wallingford
OX10 8BG
31 03 2017
 
206 Crowmarsh Hill
Crowmarsh Gifford
Wallingford
OX10 8BG
31 03 2017
 
Defence Infrastructure Organisation
10 08 2017
16 10 2017
 
Application Type
Minor (Outline)
Application Progress
Date Received  
24th March 2017
Registration Date  
28th March 2017
Start Consultation Period  
31st March 2017
End Consultation Period  
21st April 2017
Target Decision Date  
8th February 2018
Decision
Planning Permission on 8th February 2018
Conditions / Refusal Reasons
Development shall not commence until details of the reserved matters relating to landscaping have been submitted to and approved in writing by the Local Planning Authority. In the case of any reserved matter, application for approval must be made not later than the expiration of three years beginning with the date of the grant of outline planning permission. Thereafter the development shall commence not later than whichever is the later of the following dates: (a) the expiration of three years from the date of this permission; or (b) the expiration of two years from the final approval of the reserved matters, or in the case of approval on different dates, the final approval of the last such matter to be approved. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. Related application(s): P19/S2352/DIS

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 5657/1, 5657/4, 5657/3, 5657/L, 5657/2b and 2794-1, except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies. Related application(s): P19/S2352/DIS

Prior to the commencement of the development hereby approved, a schedule of all materials to be used in the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority. Reason: In the interests of the visual appearance of the development in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011. Related application(s): P19/S2352/DIS

Prior to the commencement of development detailed plans showing the existing and proposed ground levels of the site together with the slab and ridge levels of the proposed development, relative to a fixed datum point on adjoining land outside of the application site, shall be submitted to and approved in writing by the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details. Reason: To ensure a satisfactory form of development in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011. Related application(s): P19/S2352/DIS

Prior to the commencement of any site works or operations relating to the development hereby permitted, an arboricultural method statement to ensure the satisfactory protection of retained trees during the construction period shall be submitted to and approved in writing by the Local Planning Authority. Written approval must be obtained prior to commencement of any site works including demolition. The matters to be encompassed within the arboricultural method statement shall include the following:- (i) A specification for the pruning of, or tree surgery to, trees to be retained in order to prevent accidental damage by construction activities; (ii) The specification of the location, materials and means of construction of temporary protective fencing and/or ground protection in the vicinity of trees to be retained, in accordance with the recommendations of BS 5837 'Trees in relation to design, demolition and construction' and details of the timing and duration of its erection; (iii) The definition of areas for the storage or stockpiling of materials, temporary on-site parking, site offices and huts, mixing of cement or concrete, and fuel storage; (iv) The means of demolition of any existing site structures, and of the re-instatement of the area currently occupied thereby; (v) The specification of the routing and means of installation of drainage or any underground services in the vicinity of retained trees; (vi) The details and method of construction of any other structures such as boundary walls in the vicinity of retained trees and how these relate to existing ground levels; (vii) The details of the materials and method of construction of any roadway, parking, pathway or other surfacing within the RPA, which is to be of a 'no dig' construction method in accordance with the principles of Arboricultural Practice Note 12 "Through the Trees to Development", and in accordance with current industry best practice; and as appropriate for the type of roadway required in relation to its usage. (viii) Provision for the supervision of ANY works within the root protection areas of trees to be retained, and for the monitoring of continuing compliance with the protective measures specified, by an appropriately qualified arboricultural consultant, to be appointed at the developer's expense and notified to the Local Planning Authority, prior to the commencement of development; and provision for the regular reporting of continued compliance or any departure there from to the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details with the agreed measures being kept in place during the entire course of development. Reason: To safeguard trees which are visually important in accordance with Policies CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C9 and D1 of the South Oxfordshire Local Plan 2011. Related application(s): P19/S2352/DIS

Prior to the commencement of the development, a Reptile Impact Avoidance Strategy, written by a suitably qualified ecologist, shall be submitted to and approved in writing by the Local Planning Authority. The development will then be carried out in accordance with the approved strategy. Reason: To ensure that important species are not harmed during development, in accordance with Policies C6 and C8 of the SOLP, in addition to Policy CSB1 of the SOCS.

Prior to commencement of development, the existing means of access onto Crowmarsh Hill shall be improved and laid out and constructed strictly in accordance with the local highway authority's specifications and all ancillary works specified shall be undertaken. Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.

Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan 5657/2b and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times. Reason: In the interests of highway safety and in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.

No building shall be occupied until the whole of the roads and footpaths shown on the layout plan accompanying the application, and all surface water drainage works have been laid out, constructed and completed in accordance with a specification to be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. Reason: In the interests of highway safety and convenience in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.

Prior to the commencement of the development a phased risk assessment shall be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice. Each phase shall be submitted to and approved in writing by the Local Planning Authority. Phase 1 shall incorporate a desk study and site walk over to identify all potential contaminative uses on site, and to inform the conceptual site model. If potential contamination is identified in Phase 1 then a Phase 2 investigation shall be undertaken. Phase 2 shall include a comprehensive intrusive investigation in order to characterise the type, nature and extent of contamination present, the risks to receptors and if significant contamination is identified to inform the remediation strategy. Phase 3 requires that a remediation strategy be submitted to and approved by the LPA to ensure the site will be rendered suitable for its proposed use. Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy EP8 of the South Oxfordshire Local Plan 2011.

The development shall not be occupied until any previously approved remediation strategy has been carried out in full and a validation report confirming completion of these works has been submitted to and approved in writing by the Local Planning Authority. Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy EP8 of the South Oxfordshire Local Plan 2011.

Cranes and other tall construction equipment (including the details of obstacle lighting) shall not be used in the construction of the development unless otherwise agreed in writing by the Local Planning Authority. Reason: To ensure that construction work and construction equipment on the site and adjoining land does not obstruct air traffic movements or otherwise impede the effective operation of air traffic navigation transmitter/receiver systems.
Appeal
No appeal lodged.
Updates