The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P17/S0840/DIS,
P18/S3243/DIS,
P18/S3540/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, BLO100019980, 16.992_01, LOC100019980, 16.992_08, 16.992/14A, 16.992/15 and 16.992_09A, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P17/S0840/DIS,
P18/S3243/DISPrior to the commencement of the development hereby approved samples of all materials to be used in the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, D1 and CSQ3 of the South Oxfordshire Local Plan 2011.
Prior to first occupation of the development, the existing means of access onto the unnamed road running through Holton shall be improved and laid out and constructed strictly in accordance with the local highway authority's specifications and all ancillary works specified shall be undertaken.
Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
The proposed vision splay shall be formed, laid out and constructed in accordance with detailed plans which shall be submitted to and approved in writing by the Local Planning Authority prior to the first occupation of the development and the vision splays shall not be obstructed by any object, structure, planting or other material with a height exceeding or growing above 0.9 metres as measured from carriageway level.
Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan 16.992/14A and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.
A Construction Traffic Management Plan (CTMP) shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The approved CTMP shall be implemented prior to any works being carried out on site, and shall be maintained throughout the course of the development.
Reason: In the interests of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, particularly at morning and afternoon peak traffic times and in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
The garage accommodation hereby approved shall be retained as such and shall not be adapted for living purposes without the prior written permission of the Local Planning Authority.
Reason: In the interests of highway safety and to ensure the provision of adequate off-street car parking in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.
The development hereby permitted shall be implemented in accordance with the Recommendations contained in Chapter 5 of the Great Crested Newt Assessment (Belos Ecology Ref:446_12_10_16_dp) submitted with the application in all respects. Any variation shall be agreed in writing by the Local Planning Authority before such change is made.
Reason: To protect the important species on the site, in accordance with provisions of the NPPF and policies CSB1 of the South Oxfordshire Core Strategy 2027 and C8 of the South Oxfordshire Local Plan 2011.
The development hereby permitted shall not be occupied until surface water drainage works have been carried out in accordance with details that have been first submitted to and approved in writing by the Local Planning Authority.
Reason: To prevent pollution and flooding in accordance with Policies EP1, EP4 and EP6 of the South Oxfordshire Local Plan 2011.
The development hereby permitted shall not be occupied until foul drainage works have been carried out in accordance with details that have been first submitted to and approved in writing by the Local Planning Authority.
Reason: To prevent pollution in accordance with Policy EP1 of the South Oxfordshire Local Plan 2011.
The first floor window in 'House 4' as shown on drawing 16.992/09A serving in the bathroom and window serving the loft space on the north east elevation and the en-suite bathroom of 'House 2' as shown on drawing 16.9992/15 shall be glazed in obscure glass, and shall be fixed shut with the exception of a top hung openable fanlight, prior to the first occupation of the accommodation and it shall be retained as such thereafter.
Reason: To ensure that the development is not unneighbourly in accordance with Policies D4 and H4 of the South Oxfordshire Local Plan 2011.