The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P17/S3867/DIS,
P19/S0141/DIS,
P19/S0709/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, P07, 15352_TOPO_01, 15-1897-99-P02, 15-1897-100-P03, Sk01, P01D, P02D, P03B, P04A, P06B and P05C, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P17/S3867/DISThat all existing buildings on the site shall be demolished before the new development hereby permitted commences, and any demolished material which is not to be utilised in the new development shall be removed from the land, unless an alternative scheme for the phased demolition of the building(s) and removal of materials is first submitted to and approved in writing by the Local Planning Authority.
Reason: To ensure satisfactory comprehensive development in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P17/S3867/DISPrior to the commencement of the development hereby approved samples of all materials to be used in the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, H4 and D1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P17/S3867/DISPrior to the commencement of any site works or operations relating to the development hereby permitted, an arboricultural method statement to ensure the satisfactory protection of retained trees during the construction period shall be submitted to and approved in writing by the Local Planning Authority. Written approval must be obtained prior to commencement of any site works including demolition. The matters to be encompassed within the arboricultural method statement shall include the following:-
(i) A specification for the pruning of, or tree surgery to, trees to be retained in order to prevent accidental damage by construction activities;
(ii) The specification of the location, materials and means of construction of temporary protective fencing and/or ground protection in the vicinity of trees to be retained, in accordance with the recommendations of BS 5837 'Trees in relation to design, demolition and construction' and details of the timing and duration of its erection;
(iii) The definition of areas for the storage or stockpiling of materials, temporary on-site parking, site offices and huts, mixing of cement or concrete, and fuel storage;
(iv) The means of demolition of any existing site structures, and of the re-instatement of the area currently occupied thereby;
(v) The specification of the routing and means of installation of drainage or any underground services in the vicinity of retained trees;
(vi) The details and method of construction of any other structures such as boundary walls in the vicinity of retained trees and how these relate to existing ground levels;
(vii) The details of the materials and method of construction of any roadway, parking, pathway or other surfacing within the RPA, which is to be of a 'no dig' construction method in accordance with the principles of Arboricultural Practice Note 12 "Through the Trees to Development", and in accordance with current industry best practice; and as appropriate for the type of roadway required in relation to its usage.
(viii) Provision for the supervision of ANY works within the root protection areas of trees to be retained, and for the monitoring of continuing compliance with the protective measures specified, by an appropriately qualified arboricultural consultant, to be appointed at the developer's expense and notified to the Local Planning Authority, prior to the commencement of development; and provision for the regular reporting of continued compliance or any departure there from to the Local Planning Authority.
Thereafter the development shall be carried out in accordance with the approved details with the agreed measures being kept in place during the entire course of development.
Reason: To safeguard trees which are visually important in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C9 and D1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P17/S3867/DISPrior to the commencement of the development hereby permitted a scheme for the landscaping of the site, including the planting of live trees and shrubs, the treatment of the access road and hard standings, and the provision of boundary treatment shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall be implemented prior to the first occupation or use of development and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority.
Reason: To help to assimilate the development into its surroundings in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C9 and D1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P17/S3867/DISA construction management plan detailing measures to be taken to protect nearby residents from noise and dust shall be submitted to and approved by the Local Planning Authority prior to the commencement of any construction or demolition works. The hours of operation for such works shall be restricted to 8:00 am - 6.00 pm Monday to Friday and 8.00 am - 1.00 pm on a Saturday.
No work shall take place on Sundays or Public Holidays without the prior written authority of the Local Planning Authority.
Reason: In the interest of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, particularly at morning and afternoon peak traffic times and in accordance with Policies T1 and EP2 of the adopted South Oxfordshire Local Plan 2011.
Related application(s):
P17/S3867/DISPrior to the commencement of any development (including demolition works), a Construction
Method Statement shall be submitted to and approved in writing by the Local Planning Authority. The approved statement shall be complied with throughout the construction period, and shall provide details of the following:-
1. Vehicle parking facilities for construction workers, other site operatives and visitors.
2. Site offices and other temporary buildings;
3. Loading and unloading of plant and materials;
4. Storage of plant and materials used during construction;
5. Vehicle wheel washing facilities;
6. Measures to control the emission of dust and dirt.
7. A scheme for recycling and / or disposing of waste materials arising from the demolition and construction works.
8. Installation and maintenance of security hoarding /fencing
Reason: In the interests of visual and residential amenity and highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P17/S3867/DISExcept in the case of any building work hereby permitted, no change in the levels of the land shall take place unless in accordance with a detailed scheme which shall have been submitted to and approved in writing by the Local Planning Authority before any development commences on site. The scheme shall include details of existing and proposed ground levels.
Reason: To ensure a satisfactory form of development in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P17/S3867/DISPrior to occupation of the development hereby permitted the proposed means of access onto Mill Road is to be formed and laid out and constructed strictly in accordance with the local highway authority's specifications and all ancillary works specified shall be undertaken.
Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P17/S3867/DISPrior to the occupation of the , the existing means of access onto Mill Road shall be improved and laid out and constructed strictly in accordance with the local highway authority's specifications and all ancillary works specified shall be undertaken.
Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
The proposed vision splay shall be formed, laid out and constructed in accordance with detailed plans which shall be submitted to and approved in writing by the Local Planning Authority prior to the first occupation of the development and the vision splays shall not be obstructed by any object, structure, planting or other material with a height exceeding or growing above 0.6 metres as measured from carriageway level unless otherwise agreed in writing by the Local Planning Authority.
Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan P01D and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.
Cycle parking facilities shall be provided prior to the occupation of the development hereby approved, in accordance with details to be submitted to and approved in writing by the Local Planning Authority, prior to the commencement of development.
Reason: To encourage the use of cycles as a means of transport in accordance with Policy T2 of the South Oxfordshire Local Plan 2011.
No surface water from the development shall be discharged onto the adjoining highway
Reason: In the interests of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
Development shall not begin until a surface water drainage scheme for the site based on sustainable drainage principles and an assessment of the hydrological and hydro-geological context of the development, has been submitted to and approved in writing by the local planning authority. The scheme shall subsequently be implemented in accordance with the approved details before the development is completed. The scheme shall also include:
· Discharge Rates
· Discharge Volumes
· Maintenance and management of SUDS features
· Sizing of features - attenuation volume
· Infiltration in accordance with BRE365
· Detailed drainage layout with pipe numbers
· SUDS (detailed drainage strategy)
· Network drainage calculations
Reason: To ensure the effective drainage of the site in the interest of public health and the
avoidance of flooding in accordance with Policy EP6 of the South Oxfordshire Local Plan 2011.
Prior to the commencement of the development hereby permitted, a sustainable drainage system, based on the Infrastruct CS Flood Risk Assessment (rev C) of 13 July 2016, should be submitted to and approved in writing by the Local Planning Authority. This should specifically include more detail on the future maintenance of these, including the off-site surface water sewer.
Reason: To prevent pollution and flooding in accordance with Policies EP4 and EP6 of the South Oxfordshire Local Plan 2011.
The development hereby permitted shall not be occupied until foul drainage works have been carried out in accordance with details that have been first submitted to and approved in writing by the Local Planning Authority.
Reason: To prevent pollution in accordance with Policy EP1 of the South Oxfordshire Local Plan 2011.
The development permitted by this planning permission shall only be carried out in accordance with the approved Flood Risk Assessment (FRA) reference 15-1897.07.002, revision C, dated 13 July 2016 and prepared by Infrastruct CS Limited and the following mitigation measure detailed within the FRA:
Finished flood levels will be set no lower than 34.87 metres Above Ordnance Datum (AOD).
The scheme shall be fully implemented and subsequently maintained, in accordance with the timing/phasing arrangements embodied within the scheme, or within any other period as may subsequently be agreed, in writing, by the local planning authority.
Reason: To reduce the risk of flooding to the proposed development and future users. This is
sought in accordance with paragraph 103 of the National Planning Policy Framework (NPPF).
External lighting will only be permitted in accordance with a lighting scheme to be approved in writing by the Local Planning Authority prior to first occupation of the development. Any such lighting shall be directed downwards to prevent nuisance to adjoining residential occupiers from light spillage and shall be turned on only during the hours of operation and remain off at all other times.
Reason: To safeguard the amenity of neighbouring residents and the rural character of the countryside in accordance with Policy CSEN1 of the South Oxfordshire Core Strategy 2027 and Policy EP3 of the South Oxfordshire Local Plan 2011.
The first floor windows in the side elevation of the dwellings as shown on drawing P04A hereby permitted shall be glazed in obscure glass, and shall be fixed shut with the exception of a top hung openable fanlight, prior to the first occupation of the accommodation and it shall be retained as such thereafter.
Reason: To ensure that the development is not unneighbourly in accordance with Policies D4 and H4 or H13 of the South Oxfordshire Local Plan 2011.
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any Order revoking or re-enacting that Order), the enlargement, improvement or other alteration of any dwellinghouse as described in Schedule 2, Part 1, Class A of the Order shall not be undertaken without the prior written permission of the Local Planning Authority.
Reason: To ensure the Local Planning Authority retains control over any future development as specified in the condition in the interests of amenity and in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011.
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any Order revoking or re-enacting that Order) the provision within the curtilage of the dwelling of any building, enclosure or swimming pool as described in Schedule 2, Part 1, Class E of the Order shall not be undertaken without the prior written permission of the Local Planning Authority.
Reason: To ensure the Local Planning Authority retains control over any future development as specified in the condition in the interests of amenity in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011.
Notwithstanding the provision of Class A of Part 1 Schedule 2 of the Town and Country Planning (General Permitted Development) Order 1995 (or the equivalent provisions of any order revoking and re-enacting that Order), the garage accommodation hereby approved shall be retained as such and shall not be adapted for living purposes without the prior written permission of the Local Planning Authority.
Reason: In the interests of highway safety and to ensure the provision of adequate off-street car parking in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.
Prior to the occupation of the development a copy of the Sustainable Travel information Pack (STIP) shall be submitted to and approved in writing by the Local Planning Authority following consultation with the Local Highway Authority. The approved STIP shall then be provided to each household initially to occupy the dwellings to be built and shall include information on the alternatives to single-occupancy car use available to residents, walking and cycle route maps, discounts, and public transport information.
Reason: To promote the use of non car modes of transport in accordance with Policy CSM2 of the South Oxfordshire Core Strategy 2027
The permanent occupation of the flats shall be restricted to those persons of 55 years or over and the partners of such persons.
Reason: As the scheme provides for sheltered accommodation where parking standards are reduced in accordance with saved polices T1 and T2 of the adopted South Oxfordshire Local Plan
Where on-site parking is provided for residential dwellings, EV charging points for each parking space should be provided.
Reason : To ensure satisfactory standards of air quality for the residents of the flats and surrounding residential properties in accordance with policies G2 and EP of the a South Oxfordshire Local Plan 2011 and para's 17, 109, 110, 120 ad 124 of the NPPF.