The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P20/S0006/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 16-34-05, 16-34-04, 16-34-03, 16-34-09, 16-34-08, 16-34-06, 16-34-01, 16-34-07, 16-34-10, 16-34-02, 17425-200-01 and 16-34-11, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
The exterior of the development hereby permitted shall only be constructed in the materials specified on the plans hereby approved or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved drawing no.16-34-05 and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.
The development hereby permitted shall be implemented in accordance with the scheme of mitigation and enhancement, as stated in sections 5 and 6 of the supporting Ecological Assessment (BSG Ecology, 17/10/2016, Ref: 9087.01_R_APPR_171016), submitted with the application in all respects. Any variation shall be agreed in writing by the Local Planning Authority before such change is made.
This condition will be discharged on receipt of a letter from the project ecologist providing evidence to demonstrate that the mitigation and enhancement has been completed according to the method statement/approved report.
Reason: To protect the important species on the site, in accordance with provisions of the NPPF and policies CSB1 of the South Oxfordshire Core Strategy 2027 and C8 of the South Oxfordshire Local Plan 2011.
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any Order revoking or re-enacting that Order) the provision within the curtilage of the dwelling of any building, enclosure or swimming pool as described in Schedule 2, Part 1, Class E of the Order shall not be undertaken without the prior written permission of the Local Planning Authority.
Reason: To protect the openness of the Green Belt in accordance with Policy CSEN2 of the South Oxfordshire Core Strategy 2027 and Policies GB4 of the South Oxfordshire Local Plan 2011.
Prior to the commencement of the development a phased risk assessment shall be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice. Each phase shall be submitted to and approved in writing by the Local Planning Authority.
Phase 1 shall incorporate a desk study and site walk over to identify all potential contaminative uses on site, and to inform the conceptual site model. If potential contamination is identified in Phase 1 then a Phase 2 investigation shall be undertaken.
Phase 2 shall include a comprehensive intrusive investigation in order to characterise the type, nature and extent of contamination present, the risks to receptors and if significant contamination is identified to inform the remediation strategy.
Phase 3 requires that a remediation strategy be submitted to and approved by the LPA to ensure the site will be rendered suitable for its proposed use.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy EP8 of the South Oxfordshire Local Plan 2011.
The development shall not be occupied until any previously approved remediation strategy has been carried out in full and a validation report confirming completion of these works has been submitted to and approved in writing by the Local Planning Authority.
Reason- To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy EP8 of the South Oxfordshire Local Plan 2011.