The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P17/S3140/DIS,
P18/S0484/DIS,
P18/S3129/DIS,
P20/S4328/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 100 Rev A, 101, 201, 210, 211, 212, 213, 214, 250, 200 Rev B, 251 Rev A and 250 Rev A, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P17/S3140/DISPrior to the commencement of the development hereby approved, a schedule of all materials to be used in the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P17/S3140/DISPrior to the first occupation of the development, the existing means of access onto the unnamed road shall be improved and laid out and constructed strictly in accordance with the local highway authority's specifications and all ancillary works specified shall be undertaken.
Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P17/S3140/DISPrior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan 200 Rev B and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.
Related application(s):
P17/S3140/DISA Construction Traffic Management Plan (CTMP) shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The approved CTMP shall be implemented prior to any works being carried out on site, and shall be maintained throughout the course of the development.
Reason: In the interests of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, particularly at morning and afternoon peak traffic times and in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P17/S3140/DISThe garage accommodation hereby approved shall be retained as such and shall not be adapted for living purposes without the prior written permission of the Local Planning Authority.
Reason: In the interests of highway safety and to ensure the provision of adequate off-street car parking in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.
Related application(s):
P17/S3140/DISThe development hereby permitted shall be implemented in accordance with the scheme of mitigation and enhancement, as stated in Section 5 of the supporting Bat Emergence/Re-entry Survey Report (Enzygo Ltd, 18/01/2016, Ref CRM.192.006.EC.R.001) submitted with the application in all respects. Any variation shall be agreed in writing by the Local Planning Authority before such change is made.
Reason: To protect the important species on the site, in accordance with provisions of the NPPF and policies CSB1 of the South Oxfordshire Core Strategy 2027 and C8 of the South Oxfordshire Local Plan 2011.
Prior to the commencement of the development a phased risk assessment shall be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice. Each phase shall be submitted to and approved in writing by the Local Planning Authority.
Phase 2 shall include a comprehensive intrusive investigation in order to characterise the type, nature and extent of contamination present, the risks to receptors and if significant contamination is identified to inform the remediation strategy.
Phase 3 requires that a remediation strategy be submitted to and approved by the LPA to ensure the site will be rendered suitable for its proposed use.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy EP8 of the South Oxfordshire Local Plan 2011.
The development shall not be occupied until any previously approved remediation strategy has been carried out in full and a validation report confirming completion of these works has been submitted to and approved in writing by the Local Planning Authority.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy EP8 of the South Oxfordshire Local Plan 2011.
External lighting will only be permitted in accordance with a lighting scheme to be approved in writing by the Local Planning Authority prior to the occupation of the development. Any such lighting shall be directed downwards to prevent light spillage.
Reason: To protect the special landscape of the AONB and local residents in accordance with Policy CSEN1 of the South Oxfordshire Core Strategy 2027 and Policy EP3 of the South Oxfordshire Local Plan 2011.
That prior to the commencement of development a detailed assessment of the capacity, suitability and adequacy of the water supply serving the development shall be submitted to an approved in writing by the LPA.
Reason: To ensure that the water supply infrastructure has sufficient capacity to cope with the/this additional demand in accordance with Policy EP4 of the South Oxfordshire Local Plan 2011.
The applicant, or their agents or successors in title, shall be responsible for organising and implementing an archaeological watching brief, to be maintained during the period of construction/during any ground works taking place on the site. The watching brief shall be carried out by a professional archaeological organisation in accordance with a Written Scheme of Investigation that has first been approved in writing by the Local Planning Authority.
Reason: To safeguard the recording and inspection of matters of archaeological importance on the site in accordance with Policy CSEN3 of the South Oxfordshire Core Strategy 2027 and Policies CON11 and CON13 of the South Oxfordshire Local Plan 2011.
Following the approval of the Written Scheme of Investigation referred to in condition 13, no development shall commence on site without the appointed archaeologist being present. Once the watching brief has been completed its findings shall be reported to the Local Planning Authority, as agreed in the Written Scheme of Investigation, including all processing, research and
analysis necessary to produce an accessible and useable archive and a full report for publication.
Reason: To safeguard the recording and inspection of matters of archaeological importance on the site in accordance with Policy CSEN3 of the South Oxfordshire Core Strategy 2027 and Policies CON11 and CON13 of the South Oxfordshire Local Plan 2011.
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any Order revoking or re-enacting that Order), the enlargement, improvement or other alteration of any dwellinghouse as described in Schedule 2, Part 1, Class A of the Order shall not be undertaken without obtaining planning permission for the Local Planning Authority.
Reason: To ensure the Local Planning Authority retains control over any future development as specified in the condition in the interests of amenity and in accordance with Policy CSQ3, CSEN1 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011.
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any Order revoking or re-enacting that Order) the provision within the curtilage of the dwelling of any building, enclosure or swimming pool as described in Schedule 2, Part 1, Class E of the Order shall not be undertaken without obtaining planning permission for the Local Planning Authority.
Reason: To ensure the Local Planning Authority retains control over any future development as specified in the condition in the interests of amenity in accordance with Policy CSQ3 and CSEN1 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011.