Description
The proposal is for the development of a dwelling with associated access, parking and landscaping. In addition there will be a greenhouse, yard, double garage, workshop, cold and dry stores and a plant room. (As supported by Land Contamination Questionnaire received on 08 December 2016. As amended and supported by plans and information received on 19 December 2016, 06 January 2017, revised Appendix 1 received on 09 January 2017 and plans and information received on 31 March 2017)
Location
Land at Cherry Orchard Mongewell OX10 8DA
Grid Reference
461334/188003
Applicant
Mr R Shute
Flat E Osteriey Court
36 Hamilton Road
READING
RG1 5RD
Agent
Mr Rupert Shute
Flat E Osteriey Court
36 Hamilton Road
READING
RG1 5RD
Case Officer
Luke Veillet
Telephone: 07919 381602
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
Crowmarsh Parish Council
c/o Mr N Hannigan
24 Newnham Green
Crowmarsh Gifford
OX10 8EW
27 04 2017
15 05 2017
 
County Archaeological Services (SODC)
27 04 2017
16 05 2017
 
Countryside Officer(South Oxfordshire & Vale of White Horse)
27 04 2017
10 05 2017
 
Forestry Officer (South Oxfordshire District Council)
27 04 2017
18 05 2017
 
Highways Liaison Officer (Oxfordshire County Council)
27 04 2017
19 01 2017
 
Health & Housing - Contaminated Land
27 04 2017
10 05 2017
 
Drainage Engineer (South Oxfordshire - MONSON)
27 04 2017
23 05 2017
 
The Housemasters House
Carmel College
Mongewell
Wallingford
OX10 8BU
27 04 2017
 
Waterside House
Mongewell Park
Mongewell
Wallingford
OX10 8DA
27 04 2017
11 05 2017
 
The Rivercourt Flat
Carmel College
Mongewell
Wallingford
OX10 8BU
27 04 2017
 
Lake Farm
Mongewell Park
Mongewell
Wallingford
OX10 8DA
27 04 2017
29 12 2016
 
Flat at Sharman House
Carmel College
Mongewell
Wallingford
OX10 8BU
27 04 2017
 
Girls Boarding House
Carmel College
Mongewell
Wallingford
OX10 8BU
27 04 2017
 
Landscape Architect - SODC
27 04 2017
 
Lakeside Cottages, 2 Mongewell Park
Mongewell
Wallingford
OX10 8DA
27 04 2017
08 12 2016
 
4 Carmel Terrace, Mongewell
Wallingford
OX10 8BX
27 04 2017
19 12 2016
 
Chilterns Conservation Board
27 04 2017
17 01 2017
 
The Old Walled Garden
Mongewell Park
Wallingford
Oxfordshire
ox10 8DA
27 04 2017
04 01 2017
 
Gary Mudie -Via Email
27 04 2017
10 05 2017
 
Conservation Officer ( South )
27 04 2017
09 05 2017
 
The Gardens Trust
27 04 2017
 
Application Type
Minor (Full Application)
Application Progress
Date Received  
14th November 2016
Registration Date  
28th November 2016
Start Consultation Period  
30th November 2016
End Consultation Period  
11th May 2017
Target Decision Date  
9th June 2017
Decision
Planning Permission on 23rd June 2017
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004. Related application(s): P17/S4410/DIS

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, ENG.002.200 B, ENG.002.110 D, ENG.002.030 C, ENG.002.021 A, ENG.002.020 B, ENG.002.100 D, ENG.002.150 C, ENG.002.210 C, ENG-002-001A and ENG.002.101 C except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies. Related application(s): P17/S4410/DIS

Prior to the commencement of the development a professional archaeological organisation acceptable to the Local Planning Authority shall prepare an Archaeological Written Scheme of Investigation, relating to the application site area, which shall be submitted to and approved in writing by the Local Planning Authority. Following the approval of the Written Scheme of Investigation and prior to any demolition on the site and the commencement of the development (other than in accordance with the agreed Written Scheme of Investigation), a staged programme of archaeological evaluation and mitigation shall be carried out by the commissioned archaeological organisation in accordance with the approved Written Scheme of Investigation. The programme of work shall include all processing, research and analysis necessary to produce an accessible and useable archive and a full report for publication which shall be submitted to the Local Planning Authority. Reason: To enable an appropriate level of archaeological investigation of the area including excavation and recording, post excavation analysis and the publication of results in accordance with Policy CSEN3 of the South Oxfordshire Core Strategy 2027 and Policies G2, CON11, CON13, and CON14 of the South Oxfordshire Local Plan 2011. Related application(s): P17/S4410/DIS

Details of all boundary walls, fences and any other means of enclosure shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of any development. All such approved means of enclosure shall be erected prior to the first occupation of the development. Reason: In the interests of the visual appearance of the development in accordance with Policy CSQ3, CSEN3 and CSEN1 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011. Related application(s): P17/S4410/DIS

A scheme for the means of treatment of the hard surfaced areas shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of any development. All such approved hard surfacing shall be provided prior to the first occupation of the development. Reason: In the interests of the visual appearance of the development in accordance with Policy CSQ3, CSEN1 and CSEN3 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011. Related application(s): P17/S4410/DIS

Prior to the commencement of the development hereby approved, photographic samples of all materials to be used in the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority. Reason: In the interests of the visual appearance of the development in accordance with Policy CSQ3, CSEN3 and CSEN1 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011. Related application(s): P17/S4410/DIS

Prior to commencement of development a detailed lighting scheme for areas to be lit shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall show how and where external lighting will be installed, (through technical specifications and the provision of appropriate lighting contour plans which shall include lux levels of the lighting to be provided), so that it can be; a) Clearly demonstrated that areas to be lit have reasonably minimised light pollution, through the use of minimum levels of lighting and features such as full cut off cowls or LED. b) Clearly demonstrated that the boundary vegetation to be retained, as well as that to be planted, will not be lit in such a way as to disturb or prevent bats using their territory or having access to their breeding sites and resting places or foraging areas, through the use of minimum levels of lighting and features such as full cut off cowls or LED. All external lighting shall be installed in accordance with the specifications and locations set out in the approved scheme, and shall be maintained thereafter in accordance with the scheme. Under no circumstances should any other external lighting be installed without prior consent from the Local Planning Authority. Reason: To safeguard against light pollution in the AONB in accordance with Policy CSEN1 of the South Oxfordshire Core Strategy and saved EP3 of the South Oxfordshire Local Plan 2011. Related application(s): P17/S4410/DIS

Prior to the commencement of development, details of sustainable surface water drainage works shall be submitted and approved in writing by the Local Planning Authority. The development hereby permitted shall not be occupied until the surface water drainage works have been carried out in accordance with the approved details. Reason: To prevent pollution and flooding in accordance with Policies EP1, EP4 and EP6 of the South Oxfordshire Local Plan 2011. Related application(s): P17/S4410/DIS

Prior to the commencment of development, details of the proposed foul drainage system shall be submiited and apporved in writing by the Local Planning Authroity. The development hereby permitted shall not be occupied until the foul drainage works have been carried out in accordance the approved details. Reason: To prevent pollution in accordance with Policy EP1 of the South Oxfordshire Local Plan 2011.

Prior to the commencement of any site works or operations relating to the development hereby permitted, an arboricultural method statement to ensure the satisfactory protection of retained trees during the construction period shall be submitted to and approved in writing by the Local Planning Authority. Written approval must be obtained prior to commencement of any site works including demolition. The matters to be encompassed within the arboricultural method statement shall include the following:- (i) A specification for the pruning of, or tree surgery to, trees to be retained in order to prevent accidental damage by construction activities; (ii) The specification of the location, materials and means of construction of temporary protective fencing and/or ground protection in the vicinity of trees to be retained, in accordance with the recommendations of BS 5837 'Trees in relation to design, demolition and construction' and details of the timing and duration of its erection; (iii) The definition of areas for the storage or stockpiling of materials, temporary on-site parking, site offices and huts, mixing of cement or concrete, and fuel storage; (iv) The means of demolition of any existing site structures, and of the re-instatement of the area currently occupied thereby; (v) The specification of the routing and means of installation of drainage or any underground services in the vicinity of retained trees; (vi) The details and method of construction of any other structures such as boundary walls in the vicinity of retained trees and how these relate to existing ground levels; (vii) The details of the materials and method of construction of any roadway, parking, pathway or other surfacing within the RPA, which is to be of a 'no dig' construction method in accordance with the principles of Arboricultural Practice Note 12 "Through the Trees to Development", and in accordance with current industry best practice; and as appropriate for the type of roadway required in relation to its usage. (viii) Provision for the supervision of ANY works within the root protection areas of trees to be retained, and for the monitoring of continuing compliance with the protective measures specified, by an appropriately qualified arboricultural consultant, to be appointed at the developer's expense and notified to the Local Planning Authority, prior to the commencement of development; and provision for the regular reporting of continued compliance or any departure there from to the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details with the agreed measures being kept in place during the entire course of development. Reason: To safeguard trees which are visually important in accordance with Policies CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C9 and D1 of the South Oxfordshire Local Plan 2011.

The development hereby permitted shall be implemented in accordance with the scheme of mitigation and enhancement, as stated in section 6 of the supporting Preliminary Ecological Appraisal (Ecology By Design Ltd, February 2016, Project Code: EBD00104), submitted with the application in all respect. Any variation shall be agreed in writing by the Local Planning Authority before such change is made. This condition will be discharged on receipt of a letter from the project ecolog providing evidence to demonstrate that the mitigation has been completed according to the method statement/approved report. Reason: To ensure a no-net loss of biodiversity resource on site, in accordance with Policy CSB1 of the Core Strategy and Policy C6 of the adopted Local Plan, in addition to the provisions of the NPPF.

The development hereby permitted shall be implemented in accordance with the scheme of mitigation and enhancement, as stated in section 6 of the supporting Reptile Survey (Ecology By Design Ltd, May 2016, Project Code: EBD000104), submitted with the application in all respects. Any variation shall be agreed in writing by the Local Planning Authority before such change is made. This condition will be discharged on receipt of a letter from the project ecologist providing evidence to demonstrate that the mitigation has been completed according to the method statement/approved report. Reason: To ensure that the important species are protected on site, in accordance with Policy CSB1 of the Core Strategy and Policy C8 of the adopted Local Plan, in addition to the provisions of the NPPF.

The approved schedule and plan detailed in Landscape Management Plan B shall be implemented in accordance with the agreed programme in all respects. Any variation shall be agreed in writing by the Local Planning Authority before such change is made. Reason: To help to assimilate the development into its surroundings in accordance with Policies CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C9 and D1 of the South Oxfordshire Local Plan 2011.

The landscaping scheme as shown on the approved plans ENG.002.021 A, ENG.002.020 B shall be implemented in the first planting season after first occupation of the dwelling and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority. Reason: To help to assimilate the development into its surroundings in accordance with Policies CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C9 and D1 of the South Oxfordshire Local Plan 2011.

Prior to the first occupation of the development hereby approved a turning area and car parking spaces shall be provided within the curtilage of the site so that motor vehicles may enter, turn round and leave in a forward direction and vehicles may park off the highway. The turning area and parking spaces shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles in strict accordance with specification details to be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The turning area and car parking spaces shall be retained unobstructed except for the parking and manoeuvring of motor vehicles at all times. Reason: In the interests of highway safety and to ensure the provision of off-street car parking in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.

The vision splays shown on the approved plan ENG/002/030 Rev. C shall not be obstructed by any object, structure, planting or other material with a height exceeding or growing above 0.9 metres as measured from carriageway level. Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.

Notwithstanding the provisions of The Town and Country Planning (General Permitted Development) Order 2015 (or any order revoking and re-enacting that Order with or without modification), no development within Classes A, B, C, E and F of Part 1 to Schedule 2 of the Order shall take place. Reason: To ensure the Local Planning Authority retains control over any future development as specified in the condition in the interests of amenity and in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011.

Notwithstanding the provisions of the Town and Country Planning (General Permitted Development Order) 2015 (or any Order revoking or re-enacting that Order) the erection or construction of gates, fences, walls or other means of enclosure as described in Schedule 2, Part 2, Class A of the Order shall not be undertaken without obtaining planning permission for the Local Planning Authority. Reason: To ensure the Local Planning Authority retains control over any future development as specified in the condition in the interests of amenity in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011.
Appeal
No appeal lodged.