P16/S3401/FULApplication Type: Full Application (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Replace existing two- storey 5 bedroom house with new two- storey 5 bedroom house in a similar position, new traditional barn to serve as garage and ancillary accommodation, with outline landscaping scheme. (As per amended plans received 16.03.2017) (As per amended plans received 13.04.2017) related to P17/S3680/FUL
Location
Timbers Cottage Timbers Lane Nuffield RG9 5SY
Grid Reference
466935/187039
Applicant
Mr Michael O'Shea
Timbers Cottage, Timbers Lane
Nuffield
HENLEY-ON-THAMES
RG9 5SY
Agent
Fulcrum Building Design Ltd
9 Heneage St
London
E1 5LJ
Case Officer
Caitlin Phillpotts
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
Nuffield Parish Council
Claire Dunk
Darent Beech Lane
Woodcote
Reading
Berks
RG8 0PX
13 04 2017
19 04 2017
 
Countryside Officer(South Oxfordshire & Vale of White Horse)
17 03 2017
30 03 2017
 
Forestry Officer (South Oxfordshire District Council)
13 04 2017
10 05 2017
 
Highways Liaison Officer (Oxfordshire County Council)
17 03 2017
03 11 2016
 
Timbers Farmhouse
Nuffield
Henley-On-Thames
RG9 5SY
17 03 2017
 
1 Church Field
Nuffield
Henley-On-Thames
RG9 5ST
17 03 2017
 
Timbers Farm
Nuffield
Henley-On-Thames
RG9 5SY
17 03 2017
 
Country Roofing Supplies
Timbers Farm
Nuffield
Henley-On-Thames
RG9 5SY
17 03 2017
 
Delta Motor Sport
Timbers Farm
Nuffield
Henley-On-Thames
RG9 5SY
17 03 2017
 
2 Church Field
Nuffield
Henley-On-Thames
RG9 5ST
17 03 2017
 
3 Church Field
Nuffield
Henley-On-Thames
RG9 5ST
17 03 2017
 
14 Church Field, Nuffield
Henley-On-Thames
RG9 5ST
17 03 2017
14 11 2016
 
Application Type
Minor (Full Application)
Application Progress
Date Received  
12th October 2016
Registration Date  
18th October 2016
Start Consultation Period  
25th October 2016
End Consultation Period  
27th April 2017
Target Decision Date  
10th May 2017
Decision
Planning Permission on 10th May 2017
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, PL-01, PL-02, PL-03, PL-04, PL-06-B, PL-07-B, PL-08-B, PL-09-B, PL-10-B, PL-11-F, PL-12-E, PL-14-B, PL-15, PL-13 E and PL-05 E, except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies.

Prior to the commencement of the development hereby approved samples of all materials to be used in the making good of all buildings shown to be retained and the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority. Reason: In the interests of the visual appearance of the development in accordance with Policies CS1, CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies C4, D1, G2, G4 and H12 of the South Oxfordshire Local Plan 2011.

Prior to the commencement of development detailed plans showing the existing and proposed ground levels of the site together with the slab and ridge levels of the proposed development, relative to a fixed datum point on adjoining land outside of the application site, shall be submitted to and approved in writing by the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details. Reason: To ensure a satisfactory form of development in accordance with Policies CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, D1, H4 and D1 of the South Oxfordshire Local Plan 2011.

That a scheme for the landscaping of the site, including the planting of live trees and shrubs, shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of the development hereby permitted. The scheme shall be implemented prior to the first occupation or use as approved within 12 months of the commencement of the approved development and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority. Reason: To help to assimilate the development into its surroundings in accordance with Policies CS1, CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies C4, C9, D1, G2, G4 and H12 of the South Oxfordshire Local Plan 2011.

Prior to the commencement of any site works or operations relating to the development hereby permitted, an arboricultural method statement to ensure the satisfactory protection of retained trees during the construction period shall be submitted to and approved in writing by the Local Planning Authority. Written approval must be obtained prior to commencement of any site works including demolition. The matters to be encompassed within the arboricultural method statement shall include the following:- (i) A specification for the pruning of, or tree surgery to, trees to be retained in order to prevent accidental damage by construction activities; (ii) The specification of the location, materials and means of construction of temporary protective fencing and/or ground protection in the vicinity of trees to be retained, in accordance with the recommendations of BS 5837 'Trees in relation to design, demolition and construction' and details of the timing and duration of its erection; (iii) The definition of areas for the storage or stockpiling of materials, temporary on-site parking, site offices and huts, mixing of cement or concrete, and fuel storage; (iv) The means of demolition of any existing site structures, and of the re-instatement of the area currently occupied thereby; (v) The specification of the routing and means of installation of drainage or any underground services in the vicinity of retained trees; (vi) The details and method of construction of any other structures such as boundary walls in the vicinity of retained trees and how these relate to existing ground levels; (vii) The details of the materials and method of construction of any roadway, parking, pathway or other surfacing within the RPA, which is to be of a 'no dig' construction method in accordance with the principles of Arboricultural Practice Note 12 "Through the Trees to Development", and in accordance with current industry best practice; and as appropriate for the type of roadway required in relation to its usage. (viii) Provision for the supervision of ANY works within the root protection areas of trees to be retained, and for the monitoring of continuing compliance with the protective measures specified, by an appropriately qualified arboricultural consultant, to be appointed at the developer's expense and notified to the Local Planning Authority, prior to the commencement of development; and provision for the regular reporting of continued compliance or any departure there from to the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details with the agreed measures being kept in place during the entire course of development. Reason: To safeguard trees which are visually important in accordance with Policies CS1, CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies C4, C9, D1, G2, G4 and H12 of the South Oxfordshire Local Plan 2011.

Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with drawing no.247/16-PL-05 E and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times. Reason: In the interests of highway safety and in accordance with Policies D2, EP6, T1 and T2 of the South Oxfordshire Local Plan 2011.

Any gates provided shall be set back a minimum of 5.0 metres from the edge of the carriageway and shall open inwards into the site. Reason: To ensure that vehicles may wait clear of the highway while the gates are opened or closed in the interests of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.

The garage accommodation shown to be retained along with new garaging hereby approved shall be retained as such and shall not be adapted for living purposes without the prior written permission of the Local Planning Authority. Reason: In the interests of highway safety and to ensure the provision of adequate off-street car parking in accordance with Policies D2, T1 and T2 of the South Oxfordshire Local Plan 2011.

Both the retained outbuildings and new barn hereby permitted shall not be occupied at any time other than for purposes ancillary to the residential use of the dwelling known as Timbers Cottage. Reason: As the separate occupation of the accommodation would represent an undesirable sub-division of the property and result in inadequate standards of amenity and privacy in accordance with Policy H12 of the South Oxfordshire Local Plan 2011.

Notwithstanding the provisions of Classes A, B, C, D and E of Part 1 Schedule 2 of the Town and Country Planning (General Permitted Development) Order 2015 (or the equivalent provisions of any order revoking and re-enacting that Order), there shall be no extension to the dwelling hereby permitted and no ancillary buildings or structures shall be erected within the curtilage of the dwelling without the prior grant of planning permission. Reason: In the interest of visual amenity and to ensure the development avoids an overdeveloped or cluttered appearance in accordance with Policies CS1, CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies C4, D1, G2, G4 and H12 of the South Oxfordshire Local Plan 2011.
Appeal
No appeal lodged.