Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, PL.0101, PL.0102, PL.0112, PL.0113, PL.0116, PL.0122, PL.0123, PL.0125, PL.0126 and PL.0115, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
A detailed specification of the type, design and external finish of all windows and external doors shall be submitted to and approved in writing by the Local Planning Authority prior to development commencing. Thereafter the development shall be carried out in accordance with the approved details.
Reason: To ensure that the appearance of the building is satisfactory in accordance with Policies CSQ3 and CSEN3 of the South Oxfordshire Core Strategy and Policies G2, D1, and CON7 of the South Oxfordshire Local Plan 2011.
Cycle parking facilities shall be provided prior to the occupation of the development hereby approved, in accordance with details to be submitted to and approved in writing by the Local Planning Authority, prior to the commencement of development. Thereafter the cycle parking facilities shall be retained.
Reason: To encourage the use of cycles as a means of transport in accordance with Policy T2 of the South Oxfordshire Local Plan 2011.
A Construction Traffic Management Plan (CTMP) shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The approved CTMP shall be implemented prior to any works being carried out on site, and shall be maintained throughout the course of the development.
Reason: In the interests of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, particularly at morning and afternoon peak traffic times and in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
All habitable rooms with windows fronting on to Bell Street at first and second floor level shall be provided with mechanical ventilation extracting air from the rear of the property. The mechanical ventilation shall be provided in accordance with a scheme which shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of the development. Such mechanical ventilation shall be retained as approved (until such time as it can be demonstrated that the concentration of nitrogen dioxide at the window to that room does not exceed the national Air Quality Objective measured as an annual mean).
Reason: To ensure satisfactory standards of air quality for the residents of the flats in accordance with policies G2 and EP1 of the adopted South Oxfordshire Local Plan 2011.