Planning Application Details

P16/S2552/OApplication Type: Outline (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Outline application for a detached dwelling with all matters reserved except access (site area extended to include access as shown on amended plans received 18 August 2016 and vision splays shown on amended plans received 15 September 2016)
Location
Land adjacent to Edgemoor Turners Green Britwell Salome OX49 5LF
Grid Reference
466933/193322
Applicant
Mrs Gillian Massey
2 Turner's  Green
Britwell Salome
WATLINGTON
OX49 5LF
Agent
Design Solutions
4  Bakery Close
Chalgrove
OX44 7QW
Case Officer
Paul Lucas
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
Britwell Salome Parish Meeting
c/o Mrs A Kerr
5 Turners Green
Brtiwell Salome
Watlington
OX49
16 09 2016
11 08 2016
 
Countryside Officer(South Oxfordshire & Vale of White Horse)
28 07 2016
12 08 2016
 
Forestry Officer (South Oxfordshire District Council)
28 07 2016
12 08 2016
 
Highways Liaison Officer (Oxfordshire County Council)
30 09 2016
30 09 2016
 
Thames Water Development Control
28 07 2016
29 07 2016
 
Waste Management Officer (District Council)
28 07 2016
08 08 2016
 
19 Turners Green
Britwell Salome
Watlington
OX49 5LF
27 07 2016
 
Britwell Fields
Turners Green
Britwell Salome
Watlington
OX49 5LF
16 09 2016
17 09 2016
 
Edgemoor
Turners Green
Britwell Salome
Watlington
OX49 5LF
16 09 2016
12 08 2016
 
Application Type
Minor (Outline)
Application Progress
Date Received  
25th July 2016
Registration Date  
18th August 2016
Start Consultation Period  
27th July 2016
End Consultation Period  
25th August 2016
Target Decision Date  
13th October 2016
Decision
Outline Planning Permission on 12th October 2016
Conditions / Refusal Reasons
Development shall not commence until details of the reserved matters [siting, appearance, layout, scale] have been submitted to and approved in writing by the Local Planning Authority. In the case of any reserved matter, application for approval must be made not later than the expiration of three years beginning with the date of the grant of outline planning permission. Thereafter the development shall commence not later than whichever is the later of the following dates: (a) the expiration of three years from the date of this permission; or (b) the expiration of two years from the final approval of the reserved matters, or in the case of approval on different dates, the final approval of the last such matter to be approved. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 224216, 224116 Rev B and 224316, except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies.

Prior to the commencement of development detailed plans showing the existing and proposed ground levels of the site together with the slab and ridge levels of the proposed development, relative to a fixed datum point on adjoining land outside of the application site, shall be submitted to and approved in writing by the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details. Reason: To ensure a satisfactory form of development in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, D1, D4 and H4 of the South Oxfordshire Local Plan 2011.

Prior to the commencement of the development hereby approved, a schedule of all materials to be used in the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority. Reason: In the interests of the visual appearance of the development in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, D1 and H4 of the South Oxfordshire Local Plan 2011.

Prior to occupation of the development hereby permitted the proposed means of access onto Turners Green is to be formed and laid out and constructed strictly in accordance with the local highway authority's specifications and all ancillary works specified shall be undertaken. Reason: In the interest of highway safety in accordance with Policies G2, H4 and T1 of the South Oxfordshire Local Plan 2011.

Before the proposed access is first used, the existing access onto Turners Green shall be permanently stopped up by the means of reinstatement of the highway verge and proposed planting to the approval of the Local Planning Authority and in accordance with the local highway authority's specifications. Thereafter the closed access shall not be used by any vehicular traffic whatsoever. Reason: In the interest of highway safety in accordance with Policies G2, H4 and T1 of the South Oxfordshire Local Plan 2011.

The proposed vision splay shall be formed, laid out and constructed in accordance with detailed plans which shall be submitted to and approved in writing by the Local Planning Authority prior to the first occupation of the development and the vision splays shall not be obstructed by any object, structure, planting or other material with a height exceeding or growing above 0.6 metres as measured from carriageway level. Reason: In the interest of highway safety in accordance with Policies G2, H4 and T1 of the South Oxfordshire Local Plan 2011.

Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan 224116 Rev.B and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times. Reason: In the interests of highway safety and in accordance with Policies G2, D2, H4, T1 and T2 of the South Oxfordshire Local Plan 2011.

Prior to the commencement of the development hereby permitted a scheme for the landscaping of the site, including the planting of live trees and shrubs, the treatment of the access road and hard standings, and the provision of boundary treatments shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall be implemented prior to the first occupation or use of development and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority. Reason: To help to assimilate the development into its surroundings in accordance with Policies CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C4, C9, D1 and H4 of the South Oxfordshire Local Plan 2011.

Prior to the commencement of any site works or operations relating to the development hereby permitted, an arboricultural method statement to ensure the satisfactory protection of retained trees during the construction period shall be submitted to and approved in writing by the Local Planning Authority. Written approval must be obtained prior to commencement of any site works including demolition. The matters to be encompassed within the arboricultural method statement shall include the following:- (i) A specification for the pruning of, or tree surgery to, trees to be retained in order to prevent accidental damage by construction activities; (ii) The specification of the location, materials and means of construction of temporary protective fencing and/or ground protection in the vicinity of trees to be retained, in accordance with the recommendations of BS 5837 'Trees in relation to design, demolition and construction' and details of the timing and duration of its erection; (iii) The definition of areas for the storage or stockpiling of materials, temporary on-site parking, site offices and huts, mixing of cement or concrete, and fuel storage; (iv) The means of demolition of any existing site structures, and of the re-instatement of the area currently occupied thereby; (v) The specification of the routing and means of installation of drainage or any underground services in the vicinity of retained trees; (vi) The details and method of construction of any other structures such as boundary walls in the vicinity of retained trees and how these relate to existing ground levels; (vii) The details of the materials and method of construction of any roadway, parking, pathway or other surfacing within the RPA, which is to be of a 'no dig' construction method in accordance with the principles of Arboricultural Practice Note 12 "Through the Trees to Development", and in accordance with current industry best practice; and as appropriate for the type of roadway required in relation to its usage. (viii) Provision for the supervision of ANY works within the root protection areas of trees to be retained, and for the monitoring of continuing compliance with the protective measures specified, by an appropriately qualified arboricultural consultant, to be appointed at the developer's expense and notified to the Local Planning Authority, prior to the commencement of development; and provision for the regular reporting of continued compliance or any departure there from to the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details with the agreed measures being kept in place during the entire course of development. Reason: To safeguard trees which are visually important in accordance with Policies CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C4, C9 and D1 and H4 of the South Oxfordshire Local Plan 2011.
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.