P15/S0313/FULApplication Type: Full Application (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Erection of 4 bedroom detached house with integrated garage
Location
Land adjacent to Kerrera High Street Culham OX14 4NB
Grid Reference
450827/195077
Applicant
Mr Derek Pink
Stoney Hedge House
Skeats Bush
East Hendred
Oxfordshire
OX12 8LH
Agent
Mr Allister Godfrey
Appledown
31 Garston Lane
Wantage
Oxfordshire
OX12 7AR
Case Officer
Marc Pullen
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
Culham Parish Council
c/o Mrs L Dalby
76 Evenlode Drive
Didcot
Oxon
OX11 7XQ
20 02 2015
 
Forestry Officer (South Oxfordshire District Council)
20 02 2015
17 03 2015
 
10 Tollgate Road
Culham
Abingdon
OX14 4NL
19 02 2015
 
6 The Glebe
Culham
Abingdon
OX14 4ND
19 02 2015
 
11 Tollgate Road
Culham
Abingdon
OX14 4NL
19 02 2015
 
Kerrera
High Street
Culham
Abingdon
OX14 4NB
19 02 2015
 
12 Tollgate Road
Culham
Abingdon
OX14 4NL
19 02 2015
 
County Archaeological Services (SODC)
03 03 2015
 
Application Type
Minor (Full Application)
Application Progress
Date Received  
5th February 2015
Registration Date  
17th February 2015
Start Consultation Period  
17th February 2015
End Consultation Period  
12th March 2015
Target Decision Date  
14th April 2015
Decision
Planning Permission on 14th April 2015
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 155-LOC1, 155-p10, 155-p12 and 155-p11A, except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies.

Prior to the commencement of the development hereby approved samples of all materials to be used in the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority unless otherwise approved under application reference P15/S1057/DIS. Reason: In the interests of the visual appearance of the development in accordance with Policy CSEN2 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011.

Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan 155-p10 and shall be constructed, laid out, surfaced, drained and completed, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times. For the avoidance of doubt: Any introduced manoeuvring area surfacing used shall be installed to be compliant with Sustainable Drainage (SuDS) regulations. Any unbound material used in production of any manoeuvring space shall be retained on site through some mechanism to be submitted for approval to the LPA and shall be constructed, laid out, surfaced drained and completed in accordance with approved plans. Reason: In the interests of highway safety and in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.

Prior to the commencement of any site works or operations relating to the development hereby permitted, an arboricultural method statement to ensure the satisfactory protection of retained trees during the construction period shall be submitted to and approved in writing by the Local Planning Authority unless otherwise approved under application reference P15/S1057/DIS. Written approval must be obtained prior to commencement of any site works including demolition. The matters to be encompassed within the arboricultural method statement shall include the following:- (i) A specification for the pruning of, or tree surgery to, trees to be retained in order to prevent accidental damage by construction activities; (ii) The specification of the location, materials and means of construction of temporary protective fencing and/or ground protection in the vicinity of trees to be retained, in accordance with the recommendations of BS 5837 'Trees in relation to design, demolition and construction' and details of the timing and duration of its erection; (iii) The definition of areas for the storage or stockpiling of materials, temporary on-site parking, site offices and huts, mixing of cement or concrete, and fuel storage; (iv) The means of demolition of any existing site structures, and of the re-instatement of the area currently occupied thereby; (v) The specification of the routing and means of installation of drainage or any underground services in the vicinity of retained trees; (vi) The details and method of construction of any other structures such as boundary walls in the vicinity of retained trees and how these relate to existing ground levels; (vii) The details of the materials and method of construction of any roadway, parking, pathway or other surfacing within the RPA, which is to be of a 'no dig' construction method in accordance with the principles of Arboricultural Practice Note 12 "Through the Trees to Development", and in accordance with current industry best practice; and as appropriate for the type of roadway required in relation to its usage. (viii) Provision for the supervision of ANY works within the root protection areas of trees to be retained, and for the monitoring of continuing compliance with the protective measures specified, by an appropriately qualified arboricultural consultant, to be appointed at the developer's expense and notified to the Local Planning Authority, prior to the commencement of development; and provision for the regular reporting of continued compliance or any departure there from to the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details with the agreed measures being kept in place during the entire course of development. Reason: To safeguard trees which are visually important in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C9 and D1 of the South Oxfordshire Local Plan 2011.

Prior to any demolition and the commencement of the development a professional archaeological organisation acceptable to the Local Planning Authority shall prepare an Archaeological Written Scheme of Investigation, relating to the application site area, which shall be submitted to and approved in writing by the Local Planning Authority unless otherwise approved under application reference P15/S1057/DIS. Reason - To safeguard the recording of archaeological matters within the site in accordance with the NPPF (2012) and saved Policy CON13 of the adopted South Oxfordshire Local Plan 2011.

Following the approval of the Written Scheme of Investigation referred to in condition 6, and prior to any demolition on the site and the commencement of the development (other than in accordance with the agreed Written Scheme of Investigation), a staged programme of archaeological evaluation and mitigation shall be carried out by the commissioned archaeological organisation in accordance with the approved Written Scheme of Investigation. The programme of work shall include all processing, research and analysis necessary to produce an accessible and useable archive and a full report for publication which shall be submitted to the Local Planning Authority unless otherwise approved under application reference P15/S1057/DIS. Reason - To safeguard the identification, recording, analysis and archiving of heritage assets before they are lost and to advance understanding of the heritage assets in their wider context through publication and dissemination of the evidence in accordance with the NPPF (2012)and saved Policy CON13 of the adopted South Oxfordshire Local Plan 2011.

Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any Order revoking or re-enacting that Order), the enlargement, improvement or other alteration of any dwellinghouse as described in Schedule 2, Part 1, Class A of the Order shall not be undertaken without the prior written permission of the Local Planning Authority. Reason: To ensure the Local Planning Authority retains control over any future development as specified in the condition in the interests of amenity and in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, D1 and H13 of the South Oxfordshire Local Plan 2011.
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.