Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 898 PL01, 898 PL02, 898 PL03, 898 PL04, 898 PL05, 898 PL06, 898 PL07, 898 PL08A and 898 PL09, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
The exterior of the development hereby permitted shall only be constructed in the materials specified on the plans hereby approved and described in the documents accompanying the application or in materials which shall previously have been approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies CSQ3 and CSEN1 of the South Oxfordshire Core Strategy 2027 and Policies G2, H4 and D1 of the South Oxfordshire Local Plan 2011.
The dwelling hereby approved shall achieve Level 4 of the Code for Sustainable Homes (or any such equivalent national measure of sustainability for house design which replaces that scheme). The dwelling shall not be occupied until a final Code Certificate has been issued for it certifying that Code Level 4 (or any such equivalent national measure of sustainability for house design which replaces that scheme) has been achieved.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy CSQ2 of the South Oxfordshire Core Strategy 2027.
Prior to the first occupation of the dwelling vision splays measuring 2.4 metres by 43 metres shall be provided to each side of the access.
Reason: In the interest of highway safety in accordance with Policies H4, T1 of the South Oxfordshire Local Plan 2011.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan 898PL07 and shall be constructed, laid out, surfaced, drained and completed, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policies H4, T1 and T2 of the South Oxfordshire Local Plan 2011.
Unless otherwise agreed by the Local Planning Authority 'LPA', development other than that required to be carried out as part of an approved remediation scheme must not commence until phases i) to iv) have been complied with, or further works have been deemed unnecessary as a result of conclusions based on risk assessments during phases i), ii) or iii), and this has been agreed upon in writing by the LPA.
Document(s) detailing the works undertaken in each phase must be submitted to and approved by the LPA in writing before any other phase commences, and before occupation of any building in relation to phase v). All phases of investigation must be designed and conducted in accordance with DEFRA and the Environment Agency's 'Model Procedures for the Management of Land Contamination, CLR 11.
i) A South Oxfordshire District Council contaminated land statement questionnaire.
ii) A preliminary risk assessment, including a site walkover and conceptual site model detailing all potential contaminants, sources and receptors.
iii) An intrusive site investigation to assess the type, nature, extent and risk(s) of any contamination identified in ii), whether or not it originates on site. It is recommended that the LPA are consulted on proposals.
iv) A detailed remediation scheme, to bring the site to a condition suitable for the intended use. The scheme shall include all works to be undertaken, proposed remediation objectives and remediation criteria, a timetable of works and site management procedures. The scheme shall also ensure that after remediation the site will not qualify as Contaminated Land under Part 2A Environmental Protection Act 1990.
v) Validation of the remediation scheme demonstrating the effectiveness of the remediation approved in iv).
If contamination is found during the course of development that was not previously identified, the development must be halted on that part of the site to the extent specified by the LPA and until the LPA are satisfied that all necessary phases above have been undertaken.
Reason: To ensure that risks from land contamination to future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors in accordance with Policy EP8 of the South Oxfordshire Local Plan 2011.
Prior to the commencement of development full details of how the spoil arising from the development hereby approved will be removed from the site shall be submitted to and approved in writing by the Local Planning Authority. The spoil shall be disposed of in accordance with the approved details, unless otherwise agreed in writing by the Local Planning Authority.
Reason: To ensure the proper disposal of the spoil generated by the development in the interests of the visual appearance of the site in accordance with Policies CSEN1 and CSQ3 of the South Oxfordshire Core Strategy and Policies G2, D1 and H4 of the South Oxfordshire Local Plan 2011.