Conditions / Refusal Reasons
That the development to which this permission relates shall be begun not later than whichever is the later of the following dates:
(a) the expiration of three years from the date of this permission; or
(b) the expiration of two years from the final approval of the reserved matters, or in the case of approval on different dates, the final approval of the last such matter to be approved.
Reason: By virtue of Section 91 to 95 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
Approval of the details of the layout, scale, appearance, the means of access thereto and the landscaping of the site (hereinafter called "the reserved matters") shall be obtained from the Local Planning Authority in writing before any development is commenced.
Reason: As the application is in outline only and is not accompanied by detailed plans and by virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
Prior to the commencement of the development hereby approved samples of all materials to be used in the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2 and D1 of the South Oxfordshire Local Plan 2011.
The dwelling(s) shall achieve Level 4 of the Code for Sustainable Homes. No dwelling shall be occupied until a final Code Certificate has been issued for it certifying that Code Level 4 has been achieved.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy CSQ2 of the South Oxfordshire Core Strategy 2027.
Prior to the occupation of the dwellings vision splays measuring 2.4 metres by 45 metres shall be provided to each side of the access and the vision splays shall not be obstructed by any object, structure, planting or other material with a height exceeding or growing above 1 metre as measured from carriageway level.
Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan and shall be constructed, laid out, surfaced, drained and completed, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.
Prior to the commencement of the development hereby permitted a scheme for the landscaping of the site, including the planting of live trees and shrubs, the treatment of the access road and hard standings, and the provision of boundary fencing and screen walling shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall be implemented as approved within 12 months of the commencement of the approved development and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority.
Reason: To help to assimilate the development into its surroundings in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C9 and D1 of the South Oxfordshire Local Plan 2011.
Unless otherwise agreed by the Local Planning Authority 'LPA', development other than that required to be carried out as part of an approved remediation scheme must not commence until phases i) to iv) have been complied with, or further works have been deemed unnecessary as a result of conclusions based on risk assessments during phases i), ii) or iii), and this has been agreed upon
in writing by the LPA.
Document(s) detailing the works undertaken in each phase must be submitted to and approved by the LPA in writing before any other phase commences, and before occupation of any building in relation to phase v). All phases of investigation must be designed and conducted in accordance with DEFRA and
the Environment Agency's 'Model Procedures for the Management of Land Contamination, CLR 11.
i) A South Oxfordshire District Council contaminated land statement questionnaire.
ii) A preliminary risk assessment, including a site walkover and conceptual site model detailing all potential contaminants, sources and receptors.
iii) An intrusive site investigation to assess the type, nature, extent and risk(s) of any contamination identified in ii), whether or not it originates on site. It is recommended that the LPA are consulted on proposals.
iv) A detailed remediation scheme, to bring the site to a condition suitable for the intended use. The scheme shall include all works to be undertaken, proposed remediation objectives and remediation criteria, a timetable of works and site management procedures. The scheme shall also ensure that after remediation the site will not qualify as Contaminated Land under Part 2A
Environmental Protection Act 1990.
v) Validation of the remediation scheme demonstrating the effectiveness of the remediation approved in iv).
If contamination is found during the course of development that was not previously identified, the development must be halted on that part of the site to the extent specified by the LPA and until the LPA are satisfied that all necessary phases above have been undertaken.
Reason: To ensure that risks from land contamination to future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors in accordance with policy EP8 of the adopted South
Oxfordshire Local Plan.
The development hereby permitted shall not be occupied until surface water drainage works have been carried out in accordance with details that have been first submitted to and approved in writing by the Local Planning Authority.
Reason: To prevent pollution and flooding in accordance with Policies EP1, EP4 and EP6 of the South Oxfordshire Local Plan 2011.