Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 11070-P02, 11070-L01A and 11070-P01A, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Prior to the beneficial occupation of the development, the parking and turning areas shall be provided in accordance with the submitted plan Drawing 11070-P01/A and shall be constructed, laid out, surfaced, drained and completed, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policies T1 and T2 and Appendix 5 (Car Parking Standards) of the South Oxfordshire Local Plan 2011.
For the avoidance of doubt: Any introduced manoeuvring area surfacing used shall be installed to be compliant with Sustainable Drainage (SuDS) regulations. Any unbound material used in production of any manoeuvring space shall be retained on site through some mechanism to be submitted for approval to the LA and shall be constructed, laid out, surfaced drained and completed in accordance with approved plans.
Prior to the commencement of the development hereby approved samples of the materials to be used for the external walls and roofs shall be submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policy G2 of the South Oxfordshire Local Plan 2011.
The dwelling(s) shall achieve Level 4 of the Code for Sustainable Homes. No dwelling shall be occupied until a final Code Certificate has been issued for it certifying that Code Level 4 has been achieved.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy CSQ2 of the South Oxfordshire Core Strategy 2027.
Prior to the commencement of any site works (including demolition or site clearance) a protected area shall be designated for all existing trees which are shown to be retained, and the trees shall be protected in accordance with a scheme which complies with the current edition of BS 5837: "Trees in relation to design, demolition and construction" that shall first have been submitted to, and approved in writing by, the Local Planning Authority. The agreed measures shall be kept in place during the entire course of development.
Reason: To safeguard trees which are visually important in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C9 and D1 of the South Oxfordshire Local Plan 2011.