The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P14/S1498/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, DHGH/13A, DHGH/14, DHGH/2, DHGH/1C, DHGH/3A, DHGH/12B and DHGH/15, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
That those buildings shown to be demolished on the plans accompanying the application shall be demolished, and any demolished material which is not to be utilised in the new development shall be removed from the land, before the development hereby permitted commences, and this provision shall apply unless an alternative scheme for the phased demolition of the building and removal of materials is first submitted to and approved in writing by the Local Planning Authority.
Reason: To ensure satisfactory comprehensive development in accordance with Policies CSEN1 and CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, H12 and D1 of the South Oxfordshire Local Plan 2011.
Prior to the commencement of the development hereby approved samples of all materials to be used in the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies CSQ3 and CSEN1 of the South Oxfordshire Core Strategy 2027 and Policies G2, H12 and D1 of the South Oxfordshire Local Plan 2011.
The dwelling shall achieve Level 4 of the Code for Sustainable Homes. The dwelling shall not be occupied until a final Code Certificate has been issued for it certifying that Code Level 4 has been achieved.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy CSQ2 of the South Oxfordshire Core Strategy 2027.