The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P13/S3498/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, OC-4C-02A and 2487 B, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P13/S3498/DISPrior to the commencement of development detailed plans showing the existing and proposed ground levels of the site together with the slab and ridge levels of the proposed development, relative to a fixed datum point on adjoining land outside of the application site, shall be submitted to and approved in writing by the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details.
Reason: To ensure a satisfactory form of development in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, H4 and D1 of the South Oxfordshire Local Plan 2011.
Prior to the commencement of the development hereby approved samples of the materials to be used for the external walls and roofs shall be submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, H4 and D1 of the South Oxfordshire Local Plan 2011.
Prior to the commencement of the development in respect of the dwellings hereby approved the new wall on the boundary of 2 Farm Road as shown on drawing 2487 B shall be constructed.
Reason: In the interests of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any Order revoking or re-enacting that Order), the enlargement, improvement or other alteration of any dwellinghouse as described in Schedule 2, Part 1, Class A of the Order shall not be undertaken without the prior written permission of the Local Planning Authority.
Reason: To ensure the Local Planning Authority retains control over any future development as specified in the condition in the interests of amenity and in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, H4 and D1 of the South Oxfordshire Local Plan 2011.
The dwelling(s) shall achieve Level 4 of the Code for Sustainable Homes. No dwelling shall be occupied until a final Code Certificate has been issued for it certifying that Code Level 4 has been achieved.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy CSQ2 of the South Oxfordshire Core Strategy 2027.
Prior to the first occupation of the development hereby approved the car parking spaces as shown on drawing 2487 B shall be provided. The car parking spaces shall be retained unobstructed except for the parking and manoeuvring of motor vehicles associated with the development hereby approved at all times.
Reason: In the interests of highway safety and to ensure the provision of off-street car parking in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.
A Construction Traffic Management Plan (CTMP) shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The approved CTMP shall be implemented prior to any works being carried out on site, and shall be maintained throughout the course of the development.
Reason: In the interests of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, particularly at morning and afternoon peak traffic times and in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
No surface water from the development shall be discharged onto the adjoining highway.
Reason: In the interests of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
Prior to the commencement of the development hereby permitted a scheme for the hard landscaping of the site, including the treatment of hard standings, and the provision of boundary fencing and screen walling shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall be implemented as approved prior to the first occupation of the dwellings.
Reason: To help to assimilate the development into its surroundings in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, H4 and D1 of the South Oxfordshire Local Plan 2011.
In connection with the implementation of this permission no construction works shall take place outside the hours of 08:00 to 18:00 Mondays to Fridays and 08:00 to 13:00 on Saturdays. Works shall not take place at all on Sundays or Bank Holidays.
Reason: To protect the occupants of nearby residential properties from noise and dust disturbance during the development of the site in accordance with Policies EP1 and EP2 of the South Oxfordshire Local Plan 2011.
Unless otherwise agreed by the Local Planning Authority 'LPA', development other than that required to be carried out as part of an approved remediation scheme must not commence until phases i) to iv) have been complied with, or further works have been deemed unnecessary as a result of conclusions based on risk assessments during phases i) or ii), and this has been agreed upon in writing by the LPA.
Document(s) detailing the works undertaken in each phase must be submitted to and approved by the LPA in writing before any other phase commences, and before occupation of any building in relation to phase iv). All phases of investigation must be designed and conducted in accordance with DEFRA and the Environment Agency's 'Model Procedures for the Management of Land Contamination, CLR 11.
i) A preliminary risk assessment, including a site walkover and conceptual site model detailing all potential contaminants, sources and receptors.
ii) An intrusive site investigation to assess the type, nature, extent and risk(s) of any contamination identified in ii), whether or not it originates on site. It is recommended that the LPA are consulted on proposals.
iii) A detailed remediation scheme, to bring the site to a condition suitable for the intended use. The scheme shall include all works to be undertaken, proposed remediation objectives and remediation criteria, a timetable of works and site management procedures. The scheme shall also ensure that after remediation the site will not qualify as Contaminated Land under Part 2A Environmental Protection Act 1990.
iv) Validation of the remediation scheme demonstrating the effectiveness of the remediation approved in iv).
If contamination is found during the course of development that was not previously identified, the development must be halted on that part of the site to the extent specified by the LPA and until the LPA are satisfied that all necessary phases above have been undertaken.
Reason: To ensure that risks from land contamination to future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors in accordance with Policy EP8 of the South Oxfordshire Local Plan 2011.
The first floor windows in the north east and south west elevations of the development hereby permitted shall be glazed in obscure glass, and shall be fixed shut with the exception of a top hung openable fanlight, prior to the first occupation of the accommodation and they shall be retained as such thereafter.
Reason: To ensure that the development is not unneighbourly in accordance with Policies D4 and H4 of the South Oxfordshire Local Plan 2011.