The works hereby permitted shall be begun not later than three years from the date of this consent.
Reason: To comply with the provisions of section 18(1) of the Planning (Listed Buildings and Conservation Areas) Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P15/S0429/DISThat the works hereby approved shall be carried out in accordance with the details shown on the following approved plans, BLO-001, Drawing_B, Drawing_D_Rev_A, Drawing_F_Rev_A, Drawing_H, Drawing_I_Rev_A and Drawing_J, except as controlled or modified by conditions of this consent.
Reason: To secure the proper planning of the historic environment in accordance with Development Plan policies.
Prior to the commencement of the works hereby approved samples of all materials and details of all paints/colour stains to be used in the external construction and finishes of the works hereby permitted shall be submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies CSQ3 and CSEN3 of the South Oxfordshire Core Strategy 2027 and Policies CON2 and CON5 of the South Oxfordshire Local Plan 2011.
All rainwater goods shall be constructed of traditionally profiled metal.
Reason: In the interests of the visual appearance of the development in accordance with Policies CSQ3 and CSEN3 of the South Oxfordshire Core Strategy 2027 and Policies CON2 and CON7 of the South Oxfordshire Local Plan 2011.