The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P13/S3198/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, SK004, SK001, SK003, SK200, SK300, 2513, SK002 P1, SK301 P1, SK101 P1, SK100 P1 and SK201 P1, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P13/S3198/DISPrior to the first occupation of the development hereby approved a turning area and car parking spaces shall be provided within the curtilage of the site so that motor vehicles may enter, turn round and leave in a forward direction and vehicles may park off the highway. The turning area and parking spaces shall be constructed, laid out, surfaced, drained and completed in strict accordance with specification details to be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The turning area and car parking spaces shall be retained unobstructed except for the parking and manoeuvring of motor vehicles at all times.
Reason: In the interests of highway safety and to ensure the provision of off-street car parking in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.
A Construction Traffic Management Plan (CTMP) shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The approved CTMP shall be implemented prior to any works being carried out on site, and shall be maintained throughout the course of the development.
Reason: In the interests of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, particularly at morning and afternoon peak traffic times and in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
No surface water from the development shall be discharged onto the adjoining highway
Reason: In the interests of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
Unless otherwise agreed by the Local Planning Authority 'LPA', development other than that required to be carried out as part of an approved remediation scheme must not commence until phases i) to iv) have been complied with, or further works have been deemed unnecessary as a result of conclusions based on risk assessments during phases i), ii) or iii), and this has been agreed upon in writing by the LPA.
Document(s) detailing the works undertaken in each phase must be submitted to and approved by the LPA in writing before any other phase commences, and before occupation of any building in relation to phase v). All phases of investigation must be designed and conducted in accordance with DEFRA and the Environment Agency's 'Model Procedures for the Management of Land Contamination, CLR 11.
i) A South Oxfordshire District Council contaminated land statement questionnaire.
ii) A preliminary risk assessment, including a site walkover and conceptual site model detailing all potential contaminants, sources and receptors
iii) An intrusive site investigation to assess the type, nature, extent and risk(s) of any contamination identified in ii), whether or not it originates on site. It is recommended that the LPA are consulted on proposals.
iv) A detailed remediation scheme, to bring the site to a condition suitable for the intended use. The scheme shall include all works to be undertaken, proposed remediation objectives and remediation criteria, a timetable of works and site management procedures. The scheme shall also ensure that after remediation the site will not qualify as Contaminated Land under Part 2A Environmental Protection Act 1990.
v) Validation of the remediation scheme demonstrating the effectiveness of the remediation approved in iv).
If contamination is found during the course of development that was not previously identified, the development must be halted on that part of the site to the extent specified by the LPA and until the LPA are satisfied that all necessary phases above have been undertaken.
Reason: To ensure that risks from land contamination to future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors in accordance with Policy EP8 of the South Oxfordshire Local Plan 2011.
Contaminated Land informatives
The chosen building control boday should be consulted if contamination is identified at the development site or if the development is being designed to be resistant to contamination. This would enable the building control body to take account of the risks to the development from contamination and to undertake any necessary inspections.
Developers should have regard to the Oxfordshire Contaminated Land Group Planning Advice Note. This document contains a " Completion Certificate" that should be completed and submitted to the Local Planning Authority when risks from land contamination have been addressed and dischargeof the contaminated land condition is being requested.
Prior to the commencement of the development hereby approved samples of all materials to be used in the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2,D1 and CON 7 of the South Oxfordshire Local Plan 2011.
That the development hereby approved shall not commence until a detailed specification of the type, design and external finish of all windows and external doors at a scale of 1:20 has been submitted to and approved in writing by the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details.
Reason: In the interests of the visual appearance of the development in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2,D1 and CON 7 of the South Oxfordshire Local Plan 2011.
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any Order revoking or re-enacting that Order), the enlargement, improvement or other alteration of any dwellinghouse as described in Schedule 2, Part 1, Class A of the Order shall not be undertaken without the prior written permission of the Local Planning Authority.
Reason: To ensure the Local Planning Authority retains control over any future development as specified in the condition in the interests of protecting the openness of the Oxford Green Belt and its visual amenity in accordance with Policy CSEN2 of the South Oxfordshire Core Strategy 2027 and Policy GB4 of the South Oxfordshire Local Plan 2011.
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any Order revoking or re-enacting that Order) the provision within the curtilage of the dwelling of any building, enclosure or swimming pool as described in Schedule 2, Part 1, Class E of the Order shall not be undertaken without the prior written permission of the Local Planning Authority.
Reason: To ensure the Local Planning Authority retains control over any future development as specified in the condition in the interests of protecting the openness of the Oxford Green Belt and its visual amenity in accordance with Policy CSEN2 of the South Oxfordshire Core Strategy 2027 and Policy GB4 of the South Oxfordshire Local Plan 2011.