Planning Application Details

P12/S2644/OApplication Type: Outline (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Erection of five dwellings comprising 1 x 2 bed, 1 x 2 bed with study, 1 x 4 bed & 2 x 4 bed Chalet Style dwellings. (As amended by plans, D&A Statement and supporting statement received 28 February 2013.)
Location
98 Park Road Didcot Oxfordshire OX11 8QR
Grid Reference
451627/189428
Applicant
Mrs O A Davis
C/o Agent
Agent
OAD
Dolce Vita
25a Clover Place
Eynsham
OX29 4QN
Case Officer
Sarah Green
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
Forestry Officer    DN
01 03 2013
14 03 2013
 
Didcot Town Council
c/o Mr D Stapleton
Council Offices
Britwell Road
DIDCOT
Oxon
OX11 7JN
01 03 2013
20 11 2012
 
12 Norreys Close
Didcot
OX11 0AS
01 03 2013
 
14 Norreys Close
Didcot
OX11 0AS
01 03 2013
 
96 Park Road
Didcot
OX11 8QR
01 03 2013
 
100 Park Road
Didcot
OX11 8QR
01 03 2013
 
Area Liaison Officer
01 03 2013
07 03 2013
 
61 Park Road
DIDCOT
OX11 8QT
01 03 2013
 
63 Park Road
DIDCOT
OX11 8QT
01 03 2013
15 03 2013
 
65 Park Road
DIDCOT
OX11 8QT
01 03 2013
14 03 2013
 
Sarah Postlethwaite
01 03 2013
12 03 2013
 
Monson Engineering Ltd.
01 03 2013
26 11 2012
 
Application Type
Minor (Outline)
Application Progress
Date Received  
5th November 2012
Registration Date  
5th November 2012
Start Consultation Period  
5th November 2012
End Consultation Period  
30th November 2012
Target Decision Date  
31st December 2012
Decision
Outline Planning Permission on 26th April 2013
Conditions / Refusal Reasons
That the development to which this permission relates shall be begun not later than whichever is the later of the following dates: (a) the expiration of three years from the date of this permission; or (b) the expiration of two years from the final approval of the reserved matters, or in the case of approval on different dates, the final approval of the last such matter to be approved. Reason: By virtue of Section 91 to 95 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.

The development hereby permitted shall not be begun until full detailed drawings illustrating the following matters have been submitted to and approved in writing by the Local Planning Authority and the development shall be carried out in accordance with such details: (i) the appearance of the new development; and (ii) the landscaping of the new development. Reason: As the application is in outline only and is not accompanied by detailed plans and by virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 12005.01 E, 12005.20 and 12005.21, except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies.

Prior to commencement of development the proposed ridge heights of the proposed dwellings relative to the ridge heights of the neighbouring properties shall be submitted to and approved in writing by the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details. Reason: To ensure that the development properly relates to the levels of adjoining development in the interest of amenity and in accordance with policy CSQ3 of the Core Strategy and Policy H4 of the South Oxfordshire Local Plan 2011.

Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any Order revoking or re-enacting that Order) the provision within the curtilage of the dwellings identified as Plot 3, Plot 4 and Plot 5 on plan ref 12005.01E of any building, enclosure or swimming pool as described in Schedule 2, Part 1, Class E of the Order shall not be undertaken without the prior written permission of the Local Planning Authority. Reason: To ensure the Local Planning Authority retains control over any future development as specified in the condition in the interests of safeguarding the protected oak trees in accordance with Policy C9 of the South Oxfordshire Local Plan 2011.

Prior to first occupation of the development hereby permitted the proposed means of access onto Park Road is to be formed and laid out and constructed strictly in accordance with detailed plans which shall first have been submitted and approved in writing by the Local Planning Authority. Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.

The proposed vision splay shall be formed, laid out and constructed in accordance with detailed plans which shall be submitted to and approved in writing by the Local Planning Authority prior to the first occupation of the development and the vision splays shall not be obstructed by any object, structure, planting or other material with a height exceeding or growing above 0.9m metres as measured from carriageway level. Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.

Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan ref 12005.01E and shall be constructed, laid out, surfaced, drained and completed, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times. Reason: In the interests of highway safety and in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.

Prior to the commencement of any site works or operations relating to the development hereby permitted, an arboricultural method statement to ensure the satisfactory protection of retained trees during the construction period shall be submitted to and approved in writing by the Local Planning Authority. Written approval must be obtained prior to commencement of any site works including demolition. The matters to be encompassed within the arboricultural method statement shall include the following:- (i) A specification for the pruning of, or tree surgery to, trees to be retained in order to prevent accidental damage by construction activities; (ii) The specification of the location, materials and means of construction of temporary protective fencing and/or ground protection in the vicinity of trees to be retained, in accordance with the recommendations of BS 5837 'Trees in relation to design, demolition and construction' and details of the timing and duration of its erection; (iii) The definition of areas for the storage or stockpiling of materials, temporary on-site parking, site offices and huts, mixing of cement or concrete, and fuel storage; (iv) The means of demolition of any existing site structures, and of the re-instatement of the area currently occupied thereby; (v) The specification of the routing and means of installation of drainage or any underground services in the vicinity of retained trees; (vi) The details and method of construction of any other structures such as boundary walls and sheds in the vicinity of retained trees and how these relate to existing ground levels; (vii) The details of the materials and method of construction of any roadway, parking, pathway or other surfacing within the RPA, which is to be of a 'no dig' construction method in accordance with the principles of Arboricultural Practice Note 12 "Through the Trees to Development", and in accordance with current industry best practice; and as appropriate for the type of roadway required in relation to its usage. (viii) Provision for the supervision of ANY works within the root protection areas of trees to be retained, and for the monitoring of continuing compliance with the protective measures specified, by an appropriately qualified arboricultural consultant, to be appointed at the developer's expense and notified to the Local Planning Authority, prior to the commencement of development; and provision for the regular reporting of continued compliance or any departure there from to the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details with the agreed measures being kept in place during the entire course of development. Reason: To safeguard trees which are visually important in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, C9 and D1 of the South Oxfordshire Local Plan 2011.

Prior to the commencement of the development details for the surface water drainage for the development shall be submitted to and approved in writing by the Local Planning Authority. The works shall be carried out in accordance with the approved details. Reason: To prevent pollution and flooding in accordance with Policies EP1, EP4 and EP6 of the South Oxfordshire Local Plan 2011.

The development hereby permitted shall not be occupied until foul drainage works have been carried out in accordance with details that have been first submitted to and approved in writing by the Local Planning Authority. Reason: To prevent pollution in accordance with Policy EP1 of the South Oxfordshire Local Plan 2011.
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.