Planning Application Details

P12/S1970/FULApplication Type: Full Application (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Variation of condition 2 of planning permission P10/W0533, to state 'that the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 6204.100 rev T1, 6204.101 Rev T1, 6204.102 Rev T1, 6204.103 Rev T1, 6204.104 Rev T1, 6204.300 Rev T1 and 6204.LOC, except as controlled or modified by conditions of this permission.'
Location
Wallingford Community Hospital Reading Road Wallingford Oxfordshire OX10 9DU
Grid Reference
460470/188937
Applicant
Oxford Health NHS Foundation Trust
Property & Capital Investment Department
Chancellor Court
Oxford Business Park South
Oxford
OX4 2GX
Agent
GBS Architects
St Thomas House
6 Becket Street
Oxford
OX1 1PP
Case Officer
Kim Gould
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
Wallingford Town Council
c/o Mr A Rogers
9 St Martin's Street
WALLINGFORD
Oxon
OX10 0AL
13 09 2012
03 10 2012
 
Health & Housing - Contaminated Land
14 09 2012
27 09 2012
 
Application Type
Minor (Full Application)
Application Progress
Date Received  
30th August 2012
Registration Date  
31st August 2012
Start Consultation Period  
31st August 2012
End Consultation Period  
3rd October 2012
Target Decision Date  
26th October 2012
Decision
Planning Permission on 23rd October 2012
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004. Related application(s): P13/S0299/DIS

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, [INSERT], except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies.

Unless otherwise agreed by the Local Planning Authority 'LPA', development other than that required to be carried out as part of an approved remediation scheme must not commence until phases i) to iv) have been complied with, or further works have been deemed unnecessary as a result of conclusions based on risk assessments during phases i) or ii), and this has been agreed upon in writing by the LPA. Document(s) detailing the works undertaken in each phase must be submitted to and approved by the LPA in writing before any other phase commences, and before occupation of any building in relation to phase iv). All phases of investigation must be designed and conducted in accordance with DEFRA and the Environment Agency's 'Model Procedures for the Management of Land Contamination, CLR 11. i) A preliminary risk assessment, including a site walkover and conceptual site model detailing all potential contaminants, sources and receptors. ii) An intrusive site investigation to assess the type, nature, extent and risk(s) of any contamination identified in ii), whether or not it originates on site. It is recommended that the LPA are consulted on proposals. iii) A detailed remediation scheme, to bring the site to a condition suitable for the intended use. The scheme shall include all works to be undertaken, proposed remediation objectives and remediation criteria, a timetable of works and site management procedures. The scheme shall also ensure that after remediation the site will not qualify as Contaminated Land under Part 2A Environmental Protection Act 1990. iv) Validation of the remediation scheme demonstrating the effectiveness of the remediation approved in iv). If contamination is found during the course of development that was not previously identified, the development must be halted on that part of the site to the extent specified by the LPA and until the LPA are satisfied that all necessary phases above have been undertaken. Reason: To ensure that risks from land contamination to future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors in accordance with Policy EP8 of the South Oxfordshire Local Plan 2011.
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.