Planning Application Details

P11/W1296Application Type: No Type (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Formation of access and new driveway.
Location
Clover Lawn 2 Church Hill Aston Tirrold OX11 9DN
Grid Reference
455584/185503
Applicant
Ms Catherine Llewellyn
2 Clover Lawn
Chalk Hill
Aston Tirrold
DIDCOT
OX11 9DN
Agent
Mrs Victoria Heath
51 Beauchamp Avenue
Leamington Spa
Warkwickshire
CV32 STB
Case Officer
Gabriella Brown
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
Aston Tirrold Parish Council
c/o Ms L Milner
Upper Thorne
Hagbourne Road
Aston Upthorpe
Didcot, Oxon
OX11 9EE
03 09 2011
20 09 2011
 
1 Chalk Hill
Aston Tirrold
DIDCOT
OX11 9DN
02 09 2011
 
Countryside Officer
03 09 2011
16 09 2011
 
Area Liaison Officer
03 09 2011
19 09 2011
 
Forestry Officer
20 09 2011
07 10 2011
 
Application Type
Other
Application Progress
Date Received  
18th August 2011
Registration Date  
18th August 2011
Start Consultation Period  
18th August 2011
End Consultation Period  
23rd September 2011
Target Decision Date  
13th October 2011
Decision
Planning Permission on 11th October 2011
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, BLO01 and BLO02, except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies.

That a scheme for the landscaping of the site, including the planting of live trees and shrubs, shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of the development hereby permitted. The scheme shall be implemented as approved within 12 months of the commencement of the approved development and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, be planted and properly maintained in a position or positions first approved by the Local Planning Authority. Reason: To help to assimilate the development into its surroundings in accordance with Policies C9 and D1 of the South Oxfordshire Local Plan 2011.

Prior to the commencement of any site works or operations relating to the development hereby permitted, an arboricultural method statement to ensure the satisfactory protection of retained trees during the construction period shall be submitted to and approved in writing by the Local Planning Authority. Written approval must be obtained prior to commencement of any site works including demolition. The matters to be encompassed within the arboricultural method statement shall include the following: (i) A specification for the pruning of, or tree surgery to, trees to be retained in order to prevent accidental damage by construction activities; (ii) The specification of the location, materials and means of construction of temporary protective fencing and/or ground protection in the vicinity of trees to be retained, in accordance with the recommendations of the current edition of BS 5837 ''Trees in relation to construction'', and details of the timing and duration of its erection; (iii) The details of the materials and method of construction of any roadway, parking, pathway or other surfacing within the RPA, which is to be of a 'no dig' construction method in accordance with the principles of Arboricultural Practice Note 12 "Through the Trees to Development'', and in accordance with current industry best practice; and as appropriate for the type of roadway required in relation to its usage. Reason: To safeguard trees which are visually important in accordance with Policies C9 and D1 of the South Oxfordshire Local Plan 2011.

Prior to the beneficial occupation of the development, the parking and turning areas shall be provided in accordance with the submitted plan Drawing Proposed Driveway, and shall be constructed, laid out, surfaced, drained and completed, and shall be retained unobstructed except for the parking of vehicles at all times. Reason: In the interest of highway safety and in accordance with Policy T1 and T2 and Appendix 5 (Car Parking Standards) of the South Oxfordshire Local Plan 2011. For the avoidance of doubt: Any introduced manoeuvring area surfacing used shall be installed to be compliant with Sustainable Drainage (SuDS) regulations. Any unbound material used in production of any manoeuvring space shall be retained on site through some mechanism to be submitted for approval to the LA and shall be constructed, laid out, surfaced drained and completed in accordance with approved plans.

No surface water from the development shall be discharged onto the adjoining highway and a scheme to prevent this occurrence shall be submitted to and approved in writing by the Local Planning Authority and constructed prior to the commencement of building operations. Reason: In the interests of highway safety and in accordance with Policies T1 and EP6 of the South Oxfordshire Local Plan 2011.

That prior to the first use of the new access the proposed means of access onto Chalk Hill shall be formed, laid out and constructed to the approval of the Highway Authority strictly in accordance with the highway authority's specifications and that all ancillary works specified shall be undertaken. Reason: In the interests of highway safety and convenience and in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.