Planning Application Details

P11/W0824Application Type: No Type (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
The creation of a new dwelling at Rectory Farm (As amended by Additional Information from Reading Agricultural Consultants received 20 July 2011).
Location
Rectory Farm Waterperry OX33 1LB
Grid Reference
462757/206453
Applicant
Mr W Selmes
Rectory Farm
The Old Yard
Waterperry
OXFORD
OX33 1LB
Agent
Simmons & Sons
32 Bell Street
HENLEY-ON-THAMES
RG9 2BH
Case Officer
Kim Gould
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
Waterperry Parish Council
c/o Mr A Cave
25 Waterperry
Oxford
OX33 1LB
14 06 2011
16 06 2011
 
23
Waterperry
OXFORD
OX33 1LB
14 06 2011
01 07 2011
 
New Rectory Farm House
Waterperry
OXFORD
OX33 1LB
14 06 2011
01 07 2011
 
Waterperry House
Waterperry
OXFORD
OX33 1JY
14 06 2011
 
Waterperry Gardens Ltd
Waterperry
OXFORD
OX33 1JZ
14 06 2011
 
County Archaeological Services
15 06 2011
24 06 2011
 
Jonathan Beale
15 06 2011
01 07 2011
 
Chezel Bird
14 06 2011
11 07 2011
 
North Lodge
26 
Waterperry
OXFORD
OX33 1LB
14 06 2011
 
Health & Housing - Contaminated Land
21 06 2011
05 07 2011
 
Oxford Green Belt Network
23 06 2011
 
Thames Water Development Cntrl
06 07 2011
 
CPRE -N J Moon (Rights of Way)
18 07 2011
 
Application Type
Minor
Application Progress
Date Received  
27th May 2011
Registration Date  
10th June 2011
Start Consultation Period  
10th June 2011
End Consultation Period  
5th July 2011
Target Decision Date  
5th August 2011
Decision
Planning Permission on 26th July 2011
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004. Related application(s): P11/W1998/DIS

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans,6000.04A,6000.02A, 6000/01 A1 except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies. Related application(s): P11/W1998/DIS

Prior to the commencement of development samples of the materials to be used for the external walls and roof shall be submitted to and approved in writing by the Local Planning Authority. Reason: To ensure that the details of the development are satisfactory in accordance with Policy D1 of the South Oxfordshire Local Plan 2011.

The occupation of the dwelling shall be limited to a person solely or mainly working, or last working, in the locality, in agriculture or forestry, or a widow or widower of such a person, and any resident's dependant. Reason: The proposed dwelling is situated in the rural area where the Local Planning Authority would not normally grant permission for such a development and this permission is granted solely in order to fulfill an essential agricultural need, in accordance with Policy A6 of the South Oxfordshire Local Plan 2011.

Unless otherwise agreed by the Local Planning Authority 'LPA', development other than that required to be carried out as part of an approved remediation scheme must not commence until phases i) to iv) have been complied with, or further works have been deemed unnecessary as a result of conclusions based on risk assessments during phases i), ii) or iii), and this has been agreed upon in writing by the LPA. Document(s) detailing the works undertaken in each phase must be submitted to and approved by the LPA in writing before any other phase commences, and before occupation of any building in relation to phase v). All phases of investigation must be designed and conducted in accordance with DEFRA and the Environment Agency's 'Model Procedures for the Management of Land Contamination, CLR 11. i) A South Oxfordshire District Council contaminated land statement questionnaire. ii) A preliminary risk assessment, including a site walkover and conceptual site model detailing all potential contaminants, sources and receptors. iii) An intrusive site investigation to assess the type, nature, extent and risk(s) of any contamination identified in ii), whether or not it originates on site. It is recommended that the LPA are consulted on proposals. iv) A detailed remediation scheme, to bring the site to a condition suitable for the intended use. The scheme shall include all works to be undertaken, proposed remediation objectives and remediation criteria, a timetable of works and site management procedures. The scheme shall also ensure that after remediation the site will not qualify as Contaminated Land under Part 2A Environmental Protection Act 1990. v) Validation of the remediation scheme demonstrating the effectiveness of the remediation approved in iv). If contamination is found during the course of development that was not previously identified, the development must be halted on that part of the site to the extent specified by the LPA and until the LPA are satisfied that all necessary phases above have been undertaken. Reason: To ensure that risks from land contamination to future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors in accordance with policy EP8 of the adopted South Oxfordshire Local Plan.

That prior to the first occupation of the dwelling hereby approved, the existing mobile home on the site which was approved under planning ref( P11/W0682)shall be removed from the site. To safeguard the character of the area in accordance with policies GB2, GB4 and H6 of the adopted SOLP
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.