The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P12/S2531/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, DB-3150/01 and DB-3150/02, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Prior to the commencement of development samples of all materials to be used in the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the local planning authority.
Reason: To safeguard the character of the area in accordance with Policy D1 of the South Oxfordshire Local Plan 2011.
That the garage doors shall be side hung and constructed in timber.
Reason: To safeguard the character and appearance of the Great Haseley Conservation Area in accordance with Policy CON7 of the South Oxfordshire Local Plan 2011.
Gas protective measures should be incorporated in to the design of the building in accordance with 1) unless a risk assessment is undertaken that demonstrates this is not necessary in accordance with 2).
1. Gas protective measures shall be incorporated into the design of the building following the measures a-b) and in accordance with current guidance on addressing the risks posed by hazardous ground gases to buildings:
a) Production of proposals for gas protective measures. These shall be submitted to and approved by the LPA before the development commences.
b) After approval by the LPA, gas protective measures shall be fully implemented and a report submitted to and approved in writing by the LPA before occupation of the site.
2. The following measures (a-c) shall be undertaken to identify and investigate any gaseous contamination on the site prior to commencement of the development and to remediate prior to occupation of the development a) A site investigation proposal to characterise any gaseous contamination at the site is submitted to and approved in writing by the LPA. This proposal shall include a phase one preliminary risk assessment, initial conceptual site model,
be in accordance with current guidance and be approved by the LPA before the investigation commences. It should be clear about what information it seeks to obtain, how this will refine the initial conceptual site model and be
comprehensive enough to enable any necessary risk assessments.
b) The approved site investigation referred to in a) above shall be fully implemented and a report submitted to the LPA for written approval. The report shall detail the works undertaken to characterise the site which must include a
risk assessment and contain a refined conceptual model in the light of the results of the investigation. N.B. If the LPA is not satisfied that the site has been adequately characterised after the first stage of investigation, further works will be required to clarify any remaining uncertainties.
c) Where unacceptable levels of gaseous contamination are identified, a proposal for a remediation scheme including measures to validate the remediation shall be submitted to and approved in writing by the LPA. Prior to occupation of the site, the approved remediation and validation schemes shall be fully implemented and a report submitted and approved in writing by the LPA.
Reason: To ensure that any gas contamination is identified and adequately addressed to ensure the safety of the development and ensure that the site is suitable for the proposed use."
If contamination is found to be present on the application site then no further development shall take place until an investigation into the nature and extent of the contamination is undertaken in line with DEFRA and the Environment Agency's Model Procedures for the Management of Land Contamination, CLR 11 and any necessary remediation is undertaken.
The Local Authority must be regularly consulted if land contamination is identified to ensure that any investigation, remediation and validation works are sufficient to ensure the site is suitable for the intended development.
That the roof lights within the west facing elevation of the outbuilding hereby approved shall be flush fitting, conservation type roof lights.
Reason: To safeguard the character and appearance of the Great Haseley Conservation Area in accordance with Policy CON7 of the South Oxfordshire Local Plan 2011.