Description
Demolition of existing dwelling.Erection of replacement one and two storey dwelling and detached 3 bay garage.
Location
Bozedown Windmill Bozedown Drive Whitchurch Hill (In the parish of Goring Heath) RG8 7PE
Grid Reference
463910/178329
Applicant
Ms Erica Robb
c/o agent
Agent
The Anderson Orr Partnership Ltd
The Studio
70 Church Road
Wheatley
OXFORD
OX33 1LZ
Case Officer
Emma Bowerman
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
Goring Heath parish council
15 Bec Tithe
Whitchurch Hill
Reading
Berks
RG8 7NP
22 03 2012
13 04 2012
 
Technology Centre
Bozedown Drive
Whitchurch Hill
READING
RG8 7QR
21 03 2012
 
Countryside Officer
22 03 2012
05 04 2012
 
Forestry Officer      DN
22 03 2012
02 04 2012
 
Application Type
Minor
Application Progress
Date Received  
9th March 2012
Registration Date  
12th March 2012
Start Consultation Period  
12th March 2012
End Consultation Period  
11th April 2012
Target Decision Date  
7th May 2012
Decision
Planning Permission on 21st May 2012
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 11031-P01, 11031-P02, 11031-P03, 11031-L01 A, 11031-P04, 11031-P05, 11031-P06, 11031-P07, 11031-P08, 15194/1, 15194/2 and 15194/3, except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies.

That all existing buildings on the site shown to be demolished on the approved plans shall be demolished before the new development hereby permitted commences, and any demolished material which is not to be utilised in the new development shall be removed from the land, unless an alternative scheme for the phased demolition of the building and removal of materials shall first have been submitted to and approved in writing by the Local Planning Authority. Reason: To ensure satisfactory comprehensive development and safeguard the character of the site and surrounding Area of Outstanding Natural Beauty in accordance with Policies H12, C2, G2 and D1 of the South Oxfordshire Local Plan 2011.

Prior to the commencement of development samples of all materials to be used in the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority. Development shall be carried out in accordance with the approved details. Reason: To safeguard the character of the site and surrounding Area of Outstanding Natural Beauty in accordance with Policies G2, G6, C2, H12 and D1 of the South Oxfordshire Local Plan 2011.

Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any Order revoking or re-enacting that Order), the enlargement of any dwellinghouse as described in Schedule 2, Part 1, Class A of the Order shall not be undertaken without the prior written permission of the Local Planning Authority. Reason: To ensure the Local Planning Authority retains control over any future development as specified in the condition in the interests of amenity and in accordance with Policies G2, C2 and D1 of the South Oxfordshire Local Plan 2011.

The measures set out in section 5 of the design statement, which accompanied the application, in respect of sustainable building, shall be implemented in accordance with the statement prior to the first occupation of the dwelling, unless as may otherwise be agreed in writing by the Local Planning Authority. Reason: To ensure sustainable development in accordance with Policy D8 of the South Oxfordshire Local Plan 2011.

Prior to the first occupation of the development, the parking and turning areas shall be provided in accordance with the approved plan 11031-P02 and shall be constructed, laid out, surfaced, drained and completed, and shall be retained unobstructed except for the parking of vehicles at all times. Reason: In the interests of highway safety and in accordance with Policies T1 and T2 and Appendix 5 (Car Parking Standards) of the South Oxfordshire Local Plan 2011.

Prior to the commencement of any site works (including demolition or site clearance) a protected area shall be designated for all existing trees which are shown to be retained, and the trees shall be protected in accordance with a scheme which complies with the current edition of BS 5837: "Trees in relation to design, demolition and construction" and shall have been submitted to, and approved in writing by, the local planning authority. The agreed measures shall be kept in place during the entire course of development Reason: To safeguard trees which are visually important in accordance with Policies C9, C2 and D1 of the South Oxfordshire Local Plan 2011.

Unless otherwise agreed by the Local Planning Authority 'LPA', development other than that required to be carried out as part of an approved remediation scheme must not commence until phases i) to iv) have been complied with, or further works have been deemed unnecessary as a result of conclusions based on risk assessments during phases i), ii) or iii), and this has been agreed upon in writing by the LPA. Document(s) detailing the works undertaken in each phase must be submitted to and approved by the LPA in writing before any other phase commences, and before occupation of any building in relation to phase v). All phases of investigation must be designed and conducted in accordance with DEFRA and the Environment Agency's 'Model Procedures for the Management of Land Contamination, CLR 11. i) A South Oxfordshire District Council contaminated land statement questionnaire. ii) A preliminary risk assessment, including a site walkover and conceptual site model detailing all potential contaminants, sources and receptors. iii) An intrusive site investigation to assess the type, nature, extent and risk(s) of any contamination identified in ii), whether or not it originates on site. It is recommended that the LPA are consulted on proposals. iv) A detailed remediation scheme, to bring the site to a condition suitable for the intended use. The scheme shall include all works to be undertaken, proposed remediation objectives and remediation criteria, a timetable of works and site management procedures. The scheme shall also ensure that after remediation the site will not qualify as Contaminated Land under Part 2A Environmental Protection Act 1990. v) Validation of the remediation scheme demonstrating the effectiveness of the remediation approved in iv). If contamination is found during the course of development that was not previously identified, the development must be halted on that part of the site to the extent specified by the LPA and until the LPA are satisfied that all necessary phases above have been undertaken. Reason: To ensure that risks from land contamination to future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors in accordance with policy EP8 of the adopted South Oxfordshire Local Plan.
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.