Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 2938/01, 2938/02, 2938/03, 2938/04A, 2938/05A, 2938/06A, 2938/07A, 2938/08A, 2938/09A, 2938/10A, 2938/11A, 2938/12A and 2938/13A, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Prior to the commencement of development samples of all materials to be used in the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the local planning authority.
Reason: To safeguard the character and appearance of the area in accordance with Policies G2, G6, C1, C2, D1 and H13 of the South Oxfordshire Local Plan 2011.
Prior to the commencement of any site works or operations relating to the development hereby permitted, an arboricultural method statement to ensure the satisfactory protection of retained trees during the construction period shall be submitted to and approved in writing by the Local Planning Authority. Written approval must be obtained prior to commencement of any site works including demolition. The matters to be encompassed within the arboricultural method statement shall include the following:
(i) A specification for the pruning of, or tree surgery to, trees to be retained in order to prevent accidental damage by construction activities;
(ii) The specification of the location, materials and means of construction of temporary protective fencing and/or ground protection in the vicinity of trees to be retained, in accordance with the recommendations of the current edition of BS 5837 ''Trees in relation to design, demolition and construction'', and details of the timing and duration of its erection;
(iii) The definition of areas for the storage or stockpiling of materials, temporary on-site parking, site offices and huts, mixing of cement or concrete, and fuel storage.
Thereafter the tree protection measures shall be in place during the course of construction.
Reason: To safeguard trees which are visually important in accordance with Policies C9 and D1 of the South Oxfordshire Local Plan 2011.