Planning Application Details

P11/E0343Application Type: No Type (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Erection of single storey 2-bedroom dwelling with timber shed, parking and turning (As amended by drawing number 101 Rev B received 8 April 2011).
Location
Land adjacent 40 - 43 Priest Close Nettlebed RG9 5AT
Grid Reference
469857/187354
Applicant
Clovercourt Homes Ltd
The Old Workshop
26 Ebury Road
RICKMANSWORTH
WD3 1BN
Agent
Archkingtech Limited
Abbeywood
9 Monks Close
Dorchester-on-Thames
WALLINGFORD
OX10 7JA
Case Officer
Paul Lucas
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
c/o Mrs D Elms
'Shamrock'
Port Hill
Nettlebed
Oxon
RG9 5RL
08 03 2011
12 04 2011
 
Area Liaison Officer
08 04 2011
14 04 2011
 
Waste Management Officer
08 03 2011
10 03 2011
 
Monson Engineering Ltd.
08 03 2011
 
Priest Hill Cottage
Priest Hill
Nettlebed
HENLEY-ON-THAMES
Oxon
RG9 5AR
07 03 2011
 
Applecross
Priest Hill
Nettlebed
HENLEY-ON-THAMES
Oxon
RG9 5AR
07 03 2011
14 03 2011
 
Dock Leaves
Priest Hill
Nettlebed
HENLEY-ON-THAMES
Oxon
RG9 5AR
07 03 2011
 
41 Priest Close
Nettlebed
HENLEY-ON-THAMES
Oxon
RG9 5AT
07 03 2011
 
43 Priest Close
Nettlebed
HENLEY-ON-THAMES
Oxon
RG9 5AT
07 03 2011
 
38 Priest Close
Nettlebed
HENLEY-ON-THAMES
Oxon
RG9 5AS
07 03 2011
 
39 Priest Close
Nettlebed
HENLEY-ON-THAMES
Oxon
RG9 5AS
07 03 2011
 
Thames Water Development Cntrl
08 03 2011
11 03 2011
 
42 Priest Close
Nettlebed
HENLEY-ON-THAMES
RG9 5AT
18 03 2011
 
40 Priest Close
Nettlebed
HENLEY-ON-THAMES
RG9 5AT
07 04 2011
 
Application Type
Minor
Application Progress
Date Received  
24th February 2011
Registration Date  
24th February 2011
Start Consultation Period  
24th February 2011
End Consultation Period  
8th April 2011
Target Decision Date  
21st April 2011
Decision
Planning Permission on 21st April 2011
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004. Related application(s): P11/E1389/DIS

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 100, 102, 103, 104, 105105, 200 and 101B, except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies. Related application(s): P11/E1389/DIS

Prior to the commencement of development detailed plans showing the existing and proposed ground levels of the site relative to a fixed datum point on adjoining land, together with the slab levels and ridge heights of the proposed buildings, shall be submitted to, and approved in writing by the Local Planning Authority and thereafter implemented in accordance with the approved details. Reason: To ensure that the development properly relates to the levels of adjoining development in the interests of amenity and in accordance with Policies G2, G6, D1, D4 and H5 of the South Oxfordshire Local Plan 2011. Related application(s): P11/E1389/DIS

Prior to the commencement of development a schedule of all materials to be used in the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the local planning authority. Reason: To safeguard the character of the area in accordance with Policies G2, G6, D1 and H5 of the South Oxfordshire Local Plan 2011. Related application(s): P11/E1389/DIS

Notwithstanding the provisions of the Town and Country (General Permitted Development Order) 1995 (or any Order revoking or re-enacting that Order), no development as specified in Schedule 2, Part 1, Classes A (extensions), B (roof extensions) or E (outbuildings) shall be undertaken without the prior written permission of the Local Planning Authority. Reason: The specific circumstances of this site warrant the Local Planning Authority having control over any further development as specified in the condition in the interests of amenity and in accordance with Policies G2, G6, D1, D4 and H5 of the South Oxfordshire Local Plan 2011. Related application(s): P11/E1389/DIS

The measures set out in the sustainability template, which accompanied the application, in respect of sustainable building, shall be implemented in accordance with the statement prior to the first occupation of the dwelling, unless as may otherwise be agreed in writing by the Local Planning Authority and thereafter retained as such. Reason: To ensure sustainable development in accordance with Policies G2, D8 and H5 of the South Oxfordshire Local Plan 2011. Related application(s): P11/E1389/DIS

Prior to the commencement of development details of refuse and recycling storage for the proposed dwelling shall be submitted to and approved in writing by the Local Planning Authority. The refuse and recycling storage shall be implemented in strict accordance with the approved details and retained thereafter. Reason: to ensure adequate provision for the management of waste in accordance with Policies G2, D10 and H5 of the South Oxfordshire Local Plan 2011. Related application(s): P11/E1389/DIS

Prior to the first occupation of the development, the parking and turning areas shall be provided in accordance with the approved plan 11/J242/PK/101/B and shall be constructed, laid out, surfaced (bound material), drained and completed, and shall be retained unobstructed except for the parking of vehicles at all times. Reason: In the interests of highway safety and in accordance with Policies G2, D2, H5, T1 and T2 and Appendix 5 (Car Parking Standards) of the South Oxfordshire Local Plan 2011. Related application(s): P11/E1389/DIS

No surface water from the development shall be discharged onto the adjoining highway and a scheme to prevent this occurrence shall be submitted to and approved in writing by the Local Planning Authority and constructed prior to the commencement of building operations. Reason: In the interests of highway safety and in accordance with Policies G2, H5, T1 and EP6 of the South Oxfordshire Local Plan 2011.

Prior to the commencement of the development hereby permitted a scheme for the landscaping of the site, including the planting of live trees and shrubs and the retention of existing hedging, the treatment of the driveway and hard standings, and the provision of boundary treatment shall be submitted to and approved in writing by the Local Planning Authority. The driveway, hard standings, and boundary treatment shall be implemented prior to occupation and thereafter retained as such. The planting scheme shall be implemented as approved within 12 months of the commencement of the approved development and thereafter be maintained in accordance with the approved scheme to the complete satisfaction of the Local Planning Authority. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, be planted and properly maintained in a position or positions first approved by the Local Planning Authority. Reason: To help to assimilate the development into its surroundings in accordance with Policies G2, G6, C9, D1 and H5 of the South Oxfordshire Local Plan 2011.

Unless otherwise agreed by the Local Planning Authority 'LPA', development other than that required to be carried out as part of an approved remediation scheme must not commence until phases i) to iv) have been complied with, or further works have been deemed unnecessary as a result of conclusions based on risk assessments during phases i), ii) or iii), and this has been agreed upon in writing by the LPA. Document(s) detailing the works undertaken in each phase must be submitted to and approved by the LPA in writing before any other phase commences, and before occupation of any building in relation to phase v). All phases of investigation must be designed and conducted in accordance with DEFRA and the Environment Agency's 'Model Procedures for the Management of Land Contamination, CLR 11. i) A South Oxfordshire District Council contaminated land statement questionnaire. ii) A preliminary risk assessment, including a site walkover and conceptual site model detailing all potential contaminants, sources and receptors. iii) An intrusive site investigation to assess the type, nature, extent and risk(s) of any contamination identified in ii), whether or not it originates on site. It is recommended that the LPA are consulted on proposals. iv) A detailed remediation scheme, to bring the site to a condition suitable for the intended use. The scheme shall include all works to be undertaken, proposed remediation objectives and remediation criteria, a timetable of works and site management procedures. The scheme shall also ensure that after remediation the site will not qualify as Contaminated Land under Part 2A Environmental Protection Act 1990. v) Validation of the remediation scheme demonstrating the effectiveness of the remediation approved in iv). If contamination is found during the course of development that was not previously identified, the development must be halted on that part of the site to the extent specified by the LPA and until the LPA are satisfied that all necessary phases above have been undertaken. Reason: To ensure that risks from land contamination to future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors in accordance with Policies G2, H4 and EP8 of the South Oxfordshire Local Plan 2011.

The development hereby permitted shall not commence until foul drainage works have been carried out in accordance with details that have been submitted to and approved in writing by the Local Planning Authority. Reason: To prevent pollution in accordance with Policies G2, EP1 and H5 of the South Oxfordshire Local Plan 2011.
Appeal
No appeal lodged.
Updates