Description
Erection of a single storey extension to school hall and erection of two freestanding canopies. Internal alterations to include re-organisation and enlargement of staffroom and relocation of P. E. store, entrance area, office and toilet
Conditions / Refusal Reasons
That the development be carried out strictly in accordance with the particulars of the development contained in application R3.0024/11 as shown on plan numbers 4621-01A, /02, 03C, /04A, /05, /06 & 07 accompanying the application except as controlled or modified by conditions of this permission, unless otherwise agreed in writing by the Deputy Director (Growth & Infrastructure).
Reason: To ensure the details of the development are carried out in accordance with the application as approved.
That development must be begun not later than the expiration of three years beginning with the date hereof.
Reason: By virtue of the provisions of Section 91 (1) (a) of the Town and Country Planning Act, 1990.
That samples of the external materials proposed to be used shall be submitted to and approved in writing by the Deputy Director (Growth & Infrastructure) prior to the commencement of development.
Reason: To ensure the materials are compatible with the surrounding development (D1:SOLP2011).
That no development shall take place until the trees on the site which are to be retained and which are adjacent to or within the development area, have been protected during building operations by means of a protective fence around the edge of the canopy of the trees in accordance with B.S. 5837: 2005. and with the written requirements (copy attached) of the Deputy Director (Growth & Infrastructure) relating to the protection of trees. Furthermore, no works or storing of plant or materials shall be carried out within the fenced area.
Reason: To ensure the protection of trees on the land and to preserve the amenities of the locality (C9: SODCLP2011).
That no development shall take place until a construction travel management plan (to include details of the site compound, delivery times for materials, contractors working hours) has been submitted to and approved in writing by the Deputy Director (Growth and Infrastructure). Any plan approved shall be implemented for the duration of the construction period.
Reason: In the interest of highway safety, the safety of school users and the amenities of the neighbouring residents (EP2, T1: SODCLP2011).