The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P11/E2366/DIS,
P11/E2368/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 9770-200-001; P11; P01 M; P02 D; P03 F; P04 C; P05 B; and P06, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P11/E2368/DISPrior to the commencement of development samples of the materials to be used for the external walls and roofs of the dwellings hereby permitted shall be submitted to and approved in writing by the Local Planning Authority.
Reason: To ensure that the details of the development are satisfactory in accordance with Policies G2, G6, D1 and H4 of the South Oxfordshire Local Plan 2011.
Related application(s):
P11/E2368/DISNotwithstanding details shown on the approved plans details of fencing and other means of enclosure for the boundaries of the site, and hardsurfacing shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of the development. Thereafter the approved fencing, other means of enclosure and hardsurfacing shall be provided prior to the occupation of the development.
Reason: In the interests of the visual appearance of the site in accordance with Policies G2, G6, D1 and H4 of the South Oxfordshire Local Plan 2011.
Related application(s):
P11/E2368/DISPrior to the commencement of any site works or operations relating to the development hereby permitted, an arboricultural method statement to ensure the satisfactory protection of retained trees and hedges during the construction period shall be submitted to and approved in writing by the Local Planning Authority. Written approval must be obtained prior to commencement of any site works including demolition. The matters to be encompassed within the arboricultural method statement shall include the following:
(i) A specification for the pruning of, or tree surgery to, trees and hedges to be retained in order to prevent accidental damage by construction activities;
(ii) The specification of the location, materials and means of construction of temporary protective fencing and/or ground protection in the vicinity of trees and hedges to be retained, in accordance with the recommendations of the current edition of BS 5837 ''Trees in relation to construction'', and details of the timing and duration of its erection;
(iii) The definition of areas for the storage or stockpiling of materials, temporary on-site parking, site offices and huts, mixing of cement or concrete, and fuel storage;
(iv) The means of demolition any existing site structures, and of the re-instatement of the area currently occupied thereby;
(v) The specification of the routing and mean of installation of drainage or any underground services in the vicinity of retained trees or hedges; Consideration will be made to avoid the sighting of utilities and service runs within the Root Protection Area (RPA) of all trees to be retained. Only where it can be demonstrated that there is no alternative location for the laying of utilities, will encroachment into the RPA be considered. Methodology for any installation works within the RPA will be provided and must be in compliance with NJUG Volume 4, 2007 'Guidelines for the planning and installation and maintenance of utility apparatus in proximity to trees'.
(vi) The details and method of construction of any other structures such as boundary walls in the vicinity of retained trees and hedges and how these relate to existing ground levels;
(vii) The details of the materials and method of construction of any roadway, parking, pathway or other surfacing within the RPA, which is to be of a 'no dig' construction method in accordance with the principles of Arboricultural Practice Note 12 "Through the Trees to Development'', and in accordance with current industry best practice; and as appropriate for the type of roadway required in relation to its usage.
(viii) Provision for the supervision of ANY works within the root protection areas of trees to be retained, and for the monitoring of continuing compliance with the protective measures specified, by an appropriately qualified arboricultural consultant, to be appointed at the developer's expense and notified to the Local Planning Authority, prior to the commencement of development; and provision for the regular reporting of continued compliance or any departure there from to the Local Planning Authority.
Thereafter the development shall be carried out in accordance with the approved details for the entire course of construction.
Reason: To safeguard trees and hedges which are visually important in accordance with Policies G2, G6, C9, D1, and H4 of the South Oxfordshire Local Plan 2011.
Related application(s):
P11/E2368/DISThat a scheme for the landscaping of the site, including the planting of live trees and shrubs, shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of the development hereby permitted. The scheme shall be implemented as approved within the first planting season following the completion of the development and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, be planted and properly maintained in a position or positions first approved by the Local Planning Authority.
Reason: To help to assimilate the development into its surroundings in accordance with Policies G2, G6, C9, D1, and H4 of the South Oxfordshire Local Plan 2011.
Related application(s):
P11/E2368/DISPrior to the commencement of development details of any external lighting to be used in the areas around the development hereby approved shall be submitted to and approved in writing by the Local Planning Authority. Thereafter no building shall be occupied until the external lighting has been installed in accordance with the approved details.
Reason: In the interests of the visual appearance of the site in accordance with Policies G2, G6, D1, and H4 of the South Oxfordshire Local Plan 2011.
Related application(s):
P11/E2368/DISPrior to the commencement of the development hereby approved a plan showing the existing and proposed ground levels and the finished floor levels of the dwellings hereby approved shall be submitted to and approved in writing by the Local Planning Authority. Such levels shall be shown in relation to a fixed and known datum point on adjoining land. Thereafter the development shall be constructed in accordance with the approved levels.
Reason: In the interests of the visual appearance of the site in accordance with Policies G2, G6, D1, and H4 of the South Oxfordshire Local Plan 2011.
Related application(s):
P11/E2368/DISDetails of surface water drainage shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of any part of the development. Thereafter the development shall be carried out in accordance with the approved details.
Reason: To prevent pollution and flooding in accordance with Policies EP1, EP4 and EP6 of the South Oxfordshire Local Plan 2011.
Related application(s):
P11/E2368/DISUnless otherwise agreed by the Local Planning Authority LPA, development other than that required to be carried out as part of an approved remediation scheme must not commence until phases i) to iv) have been complied with, or further works have been deemed unnecessary as a result of conclusions based on risk assessments during phases i), ii) or iii), and this has been agreed upon in writing by the LPA. Document(s) detailing the works undertaken in each phase must be submitted to and approved by the LPA in writing before any other phase commences, and before occupation of any building in relation to phase v). All phases of investigation must be designed and conducted in accordance with DEFRA and the Environment Agencys Model Procedures for the Management of Land Contamination, CLR 11.
i) A South Oxfordshire District Council contaminated land statement questionnaire.
ii) A preliminary risk assessment, including a site walkover and conceptual site model detailing all potential contaminants, sources and receptors.
iii) An intrusive site investigation to assess the type, nature, extent and risk(s) of any contamination identified in ii), whether or not it originates on site. It is recommended that the LPA are consulted on proposals.
iv) A detailed remediation scheme, to bring the site to a condition suitable for the intended use. The scheme shall include all works to be undertaken, proposed remediation objectives and remediation criteria, a timetable of works and site management procedures. The scheme shall also ensure that after remediation the site will not qualify as Contaminated Land under Part 2A Environmental Protection Act 1990.
v) Validation of the remediation scheme demonstrating the effectiveness of the remediation approved in iv).
If contamination is found during the course of development that was not previously identified, the development must be halted on that part of the site to the extent specified by the LPA and until the LPA are satisfied that all necessary phases above have been undertaken.
Reason: To ensure that risks from land contamination to future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors in accordance with Policy EP8 of the South Oxfordshire Local Plan 2011.
Prior to the first occupation of the development hereby approved, the existing buildings shown to be demolished on the approved drawings shall be demolished and all resultant debris removed from the site.
Reason: In the interests of the visual appearance of the site and the amenity of neighbouring occupiers in accordance with Policies G2, G6, and D1 of the South Oxfordshire Local Plan 2011.
Unless otherwise agreed in writing by the Local Planning Authority fire hydrants shall be provided in accordance with details to be submitted to and approved in writing by the Local Planning Authority prior to the commencement of any part of the development. Thereafter the fire hydrants shall be provided in accordance with the approved details prior to the first occupation of any part of the development and thereafter retained.
Reason: In the interests of fire safety in accordance with Policy D11 of the South Oxfordshire Local Plan 2011.
The dwellings hereby approved shall achieve a Code Level 3 in accordance with the requirements of the Code for Sustainable Homes: Technical Guide (or such national measure of sustainability for house design that replaces that scheme). No dwelling shall be occupied until a Final Code Certificate has been issued for it certifying that Code Level 3 has been achieved.
Reason: To ensure sustainable design and construction in accordance with Policy D8 of the South Oxfordshire Local Plan 2011.
The first floor level windows in the side elevations of Plots 7 and 8 shall be fitted with obscure glass before the respective dwelling is occupied and the obscure glazing shall thereafter be retained in position to the satisfaction of the Local Planning Authority.
Reason: In the interests of the amenity of the neighbouring properties in accordance with Policies D4 and H4 of the South Oxfordshire Local Plan 2011.
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any Order revoking or re-enacting that Order), the enlargement, of any dwellinghouse as described in Schedule 2, Part 1, Class A and B of the Order shall not be undertaken in relation to the dwellings shown on drawing P01 M as Plots 1, 2, 3, 4 and 6 unless a planning application for the development has been submitted to and approved by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development, neighbouring amenity, and housing mix in accordance with Policies G2, G6, D1, H4 and H7 of the South Oxfordshire Local Plan 2011.
The hours of work for all contractors for the duration of the site development shall, unless otherwise agreed in writing by the Local Planning Authority, be limited to 7:30am to 6:00pm on Mondays to Fridays, 8:00am to 1:00pm on Saturdays and no work shall be carried out on Sundays or Bank Holidays.
Reason: To protect the occupants of nearby residential properties from noise and dust disturbance during the development of the site in accordance with Policies EP1 and EP2 of the South Oxfordshire Local Plan 2011.
Details of measures to control noise and dust from construction activities associated with the development hereby approved shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development.
Reason: To protect the amenities of nearby residential properties in accordance with Policy EP1 and EP2 of the South Oxfordshire Local Plan 2011.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the submitted plan Drawing P01 M, and shall be constructed, laid out, surfaced, drained and completed, and shall be retained unobstructed except for the parking of vehicles at all times.
Reason: in the interest of highway safety and in accordance with Policy T1 and T2 and Appendix 5 (car Parking Standards) of the South Oxfordshire Local Plan 2011.
Prior to the occupation of any of the dwellings hereby approved vision splays measuring 2.4 x 70 metres shall be provided to each of the sides of the accesses and the land within the splays shall not be raised or vegetation allowed to grow above a minimum height of 900mm above the carriageway.
Reason: In the interest of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
The development hereby approved shall be designed and constructed to meet Secure by Design Part 2 Standards for physical security.