Planning Application Details

P10/W1956Application Type: No Type (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Change of use of existing building and yard to builder's merchant.
Location
Harveys Coachworks Ltd, Beadle Trading Estate Hithercroft Road Wallingford OX10 9DG
Grid Reference
459758/189279
Applicant
Blanchford Building Supplies Ltd
59 Windmill Road
Headington
OXFORD
OX3 7BS
Agent
Upfield Developments Limited
School Lane House
Moreton
THAME
OX9 2HX
Case Officer
Kim Gould
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
c/o Mr A Rogers
9 St Martin's Street
WALLINGFORD
Oxon
OX10 0AL
13 01 2011
02 02 2011
 
Marshalls Industrial Ltd
Beadle Trading Estate
Hithercroft Road
WALLINGFORD
OX10 9DG
12 01 2011
 
Precise Filling Ltd
Beadle Trading Estate
Hithercroft Road
WALLINGFORD
OX10 9DG
12 01 2011
 
Health & Housing - Env. Protection Team
12 01 2011
19 01 2011
 
Area Liaison Officer
13 01 2011
20 01 2011
 
Health & Housing - Contaminated Land
24 01 2011
08 02 2011
 
Application Type
Minor
Application Progress
Date Received  
22nd December 2010
Registration Date  
10th January 2011
Start Consultation Period  
10th January 2011
End Consultation Period  
11th February 2011
Target Decision Date  
7th March 2011
Decision
Planning Permission on 4th March 2011
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004. Related application(s): P11/W0544/DIS

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans,1022/01, except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies. Related application(s): P11/W0544/DIS

Prior to the first occupation of the development a turning area and car parking spaces shall be provided within the curtilage of the site so that motor vehicles may enter, turn round and leave in a forward direction and vehicles may park off the highway. The turning area and parking spaces shall be constructed, laid out, surfaced, drained and completed in strict accordance with specification details to be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The turning area and car parking spaces shall be retained unobstructed except for the parking and manoeuvring of motor vehicles at all times. Reason: In the interests of highway safety and to ensure the provision of off-street car parking in accordance with Policies T1 and T2 and Appendix 5 (Car Parking Standards) of the South Oxfordshire Local Plan 2011.

Unless otherwise agreed by the Local Planning Authority 'LPA', development other than that required to be carried out as part of an approved remediation scheme must not commence until phases i) to iv) have been complied with, or further works have been deemed unnecessary as a result of conclusions based on risk assessments during phases i), ii) or iii), and this has been agreed upon in writing by the LPA. Document(s) detailing the works undertaken in each phase must be submitted to and approved by the LPA in writing before any other phase commences, and before occupation of any building in relation to phase v). All phases of investigation must be designed and conducted in accordance with DEFRA and the Environment Agency's 'Model Procedures for the Management of Land Contamination, CLR 11. i) A South Oxfordshire District Council contaminated land statement questionnaire. ii) A preliminary risk assessment, including a site walkover and conceptual site model detailing all potential contaminants, sources and receptors. iii) An intrusive site investigation to assess the type, nature, extent and risk(s) of any contamination identified in ii), whether or not it originates on site. It is recommended that the LPA are consulted on proposals. iv) A detailed remediation scheme, to bring the site to a condition suitable for the intended use. The scheme shall include all works to be undertaken, proposed remediation objectives and remediation criteria, a timetable of works and site management procedures. The scheme shall also ensure that after remediation the site will not qualify as Contaminated Land under Part 2A Environmental Protection Act 1990. v) Validation of the remediation scheme demonstrating the effectiveness of the remediation approved in iv). If contamination is found during the course of development that was not previously identified, the development must be halted on that part of the site to the extent specified by the LPA and until the LPA are satisfied that all necessary phases above have been undertaken. Reason: To ensure that risks from land contamination to future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors in accordance with Policy EP8 of the South Oxfordshire Local Plan 2011.
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.