The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P11/W2093/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 1017-03-C - Site Plan Existing, 1017-06, 1017-07 and 1017-04G, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P11/W2093/DISThat a scheme for the landscaping of the site, including the planting of live trees and shrubs, shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of the development hereby permitted. The scheme shall be implemented as approved within 12 months of the commencement of the approved development and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, be planted and properly maintained in a position or positions first approved by the Local Planning Authority.
Reason: To help to assimilate the development into its surroundings in accordance with Policies C9 and D1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P11/W2093/DISPrior to the commencement of any site works (including demolition or site clearance) a protected area shall be designated for all existing trees which are shown to be retained, and the trees shall be protected in accordance with a scheme which complies with the current edition of BS 5837: "Trees in Relation to Construction" and shall have been submitted to, and approved in writing by, the local planning authority. The agreed measures shall be kept in place during the entire course of development
Reason: To safeguard trees which are visually important in accordance with Policies C9 and D1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P11/W2093/DISPrior to the first occupation of the development, the parking and turning areas shall be provided in accordance with the approved plan 1017 04 G and shall be constructed, laid out, surfaced (bound material), drained and completed, and shall be retained unobstructed except for the parking of vehicles at all times.
Reason: In the interests of highway safety and in accordance with Policies T1 and T2 and Appendix 5 (Car Parking Standards) of the South Oxfordshire Local Plan 2011.
For the avoidance of doubt: Any introduced manoeuvring area surfacing used shall be installed
to be compliant with Sustainable Drainage (SuDS) regulations. Any unbound material used in production of any manoeuvring space shall be retained on site through some mechanism to be submitted for approval to the LA and shall be constructed, laid out, surfaced drained and completed in accordance with approved plans.
Informatory 1: This planning application will I believe fall under the Flood and Water Management Act 2010, which states that if more than 2 properties or industrial developments drain to a joint SUDs (Sustainable Drainage feature), then that feature is to be adopted by the Lead Flood Authority / SUDs Adoption Body (SAB).
A drawing shall to be submitted for approval to the LPA of the modifications to be carried out to the footway external to the site, (including pedestrian guard railing) these modifications shall be conducted in accordance with the approved drawing prior to beneficial use of the implementation of the planning permission and for the avoidance of doubt approval will only be granted for works which are in accordance with DDA legislation.
Reason: in the interest of highway safety and in accordance with Policy T1 and T2 and Appendix 5 (Car Parking Standards) of the South Oxfordshire Local Plan 2011.
NOTE: It is recommended that these works are carried out under a Unilateral Undertaking agreement with OCC.