The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P10/W0939/DISPrior to the commencement of development samples of the materials to be used for the external walls and roof shall be submitted to and approved in writing by the Local Planning Authority.
Reason: To ensure that the details of the development are satisfactory in accordance with Policy D1 of the South Oxfordshire Local Plan 2011.
Related application(s):
P10/W0939/DISNo development shall commence until a phased contaminated land risk assessment including formulation of any necessary remediation proposals has been completed. The development shall then not be occupied until all approved remediation works are completed. All phases need to be undertaken by a person competent in contaminated land, in accordance with Defra and the Environment Agency's 'Model Procedures for the Management of Contaminated Land, CLR11' and be approved in writing by the Local Planning Authority (LPA). Consulting the LPA with proposals for each phase is recommended.
Phase 1 shall incorporate a desk study and site walk over to identify all potential contaminative uses on site and to inform the preliminary conceptual site model. If potential contamination is identified then Phase 2 shall be undertaken.
Phase 2 shall include a comprehensive intrusive investigation in order to characterise the type, nature and extent of contamination present, the risks to receptors and, where necessary, to inform the remediation strategy proposals. If significant contamination is found then Phase 3 shall be undertaken.
Phase 3 requires production of a remediation and validation scheme to ensure the site is rendered suitable for its proposed use. The remediation shall be carried out in accordance with a scheme and timetable first agreed in writing by the LPA.
Phase 4 requires a full validation report detailing the measures carried out to ensure compliance with any approved remediation scheme in Phase 3 to be submitted to and approved in writing by the LPA.
All implemented works shall be maintained in place thereafter.
Reason: To ensure that any ground, water and gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure that the site is suitable for the proposed use in accordance with Policy EP8 of the South Oxfordshire Local Plan 2011.
That, within 3 months of the occupation of the new dwelling, the existing bungalow shall be demolished and the materials removed from the land.
Reason: To ensure satisfactory comprehensive development in accordance with Policy H12 of the South Oxfordshire Local Plan 2011.
The measures set out in the design and access statement, which accompanied the application, in respect of sustainable building, to attain a Level 1 star rating of the Code for Sustainable Homes shall be implemented in accordance with the statement prior to the first occupation of any unit, unless as may otherwise be agreed in writing by the Local Planning Authority.
Reason: To ensure sustainable development in accordance with Policy D8 of the South Oxfordshire Local Plan 2011.