That the works hereby permitted shall be begun before the expiration of three years from the date of this consent.
Reason: By virtue of Section 18 of the Planning (Listed Buildings and Conservation Areas) Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That before any work is undertaken in pursuance of this consent, such steps shall be taken and such works shall be carried out to secure the safety and stability of the building during the alterations, and to provide protection for the building against the weather during the progress of the works.
Reason: To secure the safety and protection of the listed building in accordance with Policy CON1 of the adopted South Oxfordshire Local Plan.
That samples of all materials to be used in the external construction and finishes of the works hereby permitted shall be submitted to and approved in writing by the Local Planning Authority before the works are commenced.
Reason: To safeguard the historic character of the building in accordance with Policy CON3 of the adopted South Oxfordshire Local Plan.
Related application(s):
P09/W0469/DISThat works shall not begin until a detailed specification of the type, design and external finish of all windows and external doors has been submitted to and approved in writing by the Local Planning Authority.
Reason: To safeguard the historic character of the building in accordance with Policy CON3 of the adopted South Oxfordshire Local Plan.
Related application(s):
P09/W0469/DIS