Conditions / Refusal Reasons
That the development must be begun not later than the expiration of three years beginning with the date of this permission and if this condition is not complied with this permission shall lapse.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That samples of all materials to be used in the external construction and finishes of the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority before the development is commenced.
Reason: To safeguard the character of the area in accordance with Policy H4 of the South Oxfordshire Local Plan.
That the parking provision shall be as shown on the deposited drawing 130 Rev B all constructed, surfaced and laid out, retained and maintained.
Reason: To comply with the Local Planning Authority's vehicle parking standards in accordance with Policy T1 of the South Oxfordshire Local Plan.
That prior to the commencement of development, full details of the existing ground levels on the site and the proposed slab level of the new dwellings shall be submitted to and approved in writing by the Local Planning Authority. The works shall be carried out in accordance with the approved plans.
Reason: To ensure that the details of development are satisfactory in accordance with Policy H4 of the South Oxfordshire Local Plan.
That notwithstanding the provisions of Article 3 of, and Classes A, B, C or E of Part 1 of Schedule 2 to the Town and Country Planning (General Permitted Development) Order 1995 (or any order revoking or re-enacting that Order) no extension, additional windows, alteration to roof or new ancillary buildings within the curtilage shall be provided unless planning permission has first been granted by the Local Planning Authority on a formal application in respect thereof.
Reason: To ensure that the details of development are satisfactory in accordance with Policy H4 of the South Oxfordshire Local Plan.
That the development shall not take place until the Local Planning Authority are satisfied that contamination has been investigated and remedial action agreed by the Local Planning Authority. The site shall then not be occupied until the following action is implemented and approved by the Local Planning Authority.
i. "The following measures (a-d) shall be undertaken to investigate and remediate any contamination on the site prior to commencement of the development:
a) A desk study shall be submitted to and approved in writing by the Local Planning Authority. This study shall be conducted fully in line with the approach indicated in BS 10175: 2001 (Investigation of potentially contaminated sites - code of practice). The study shall include the identification of all previous site uses, potential contaminants that might reasonably be expected given those uses and other relevant information. If contamination is suspected at the site the information obtained must then be used to formulate an initial conceptual model for the site including all potential contaminant sources, pathways and receptors.
b) Where contamination is identified as having the potential to be present in a) above, proposals for a site investigation to characterise the site must be submitted to and approved in writing by the Local Planning Authority. This proposal shall be designed having regard to the approved desk study and BS 10175. It should be clear about what information it seeks to obtain and how this will refine the initial conceptual model for the site.
c) The approved site investigation referred to on b) above shall be fully implemented and a report submitted to the Local Planning Authority for written approval. The report shall be in line with BS 10175 and detail the works undertaken to characterise the site and contain a refined conceptual model in the light of the results of the investigation. N.B. If the Local Planning Authority is not satisfied that the site has been adequately characterised after the first stage of investigation, further works will be required to clarify any remaining uncertainties.
d) Where unacceptable levels of contamination are identified, a remediation scheme shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall incorporate details of the procedures and documentation employed to validate the remediation measures identified in c) above.
ii. Prior to occupation of the site, the approved remediation and validation schemes in d) above shall be fully implemented and a report submitted and approved in writing by the Local Planning Authority.
Reason: To ensure that any ground and water contamination is identified and adequately addressed to ensure the safety of the development, the environment and the public and ensure that the site is suitable for the proposed use in accordance with Policy EP8 of the South Oxfordshire Local Plan.
That the garages shall be retained for the purpose of garaging vehicles/bikes and shall not be used for storage purposes only.
Reason: To ensure that sufficient car parking is available on site in the interests of highway safety in accordance with Policy T2 of the South Oxfordshire Local Plan.