Conditions / Refusal Reasons
That the development must be begun not later than the expiration of three years beginning with the date of this permission and if this condition is not complied with this permission shall lapse.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
The materials to be used for the external walls and roof shall be of the same colour, type and texture as those used on the existing building.
Reason: In the interests of the visual appearance of the building in accordance with Policies G2, G6, D1 and C2 of the South Oxfordshire Local Plan 2011.
All new windows, and rainwater goods shall match those of the existing building in type, design and external finish.
Reason: In the interests of the visual appearance of the building in accordance with Policies G2, G6, D1 and C2 of the South Oxfordshire Local Plan 2011.
No development or other operations shall commence on site until details of a tree and landscape protection scheme have been submitted to and approved in writing by the Local Planning Authority. The scheme shall include a method statement as to how the soakaways will be installed and shall include positions and specifications of temporary fencing to be erected. No excavations for services, storage of materials, parking of vehicles, excavation of soils or materials shall take place within the area designated as being protected. The approved tree and landscape protection scheme shall be carried out concurrently with the development of the site.
Reason: To ensure the protection of trees on and adjacent to the site in accordance with Policy C9 of the South Oxfordshire Local Plan 2011.