Planning Application Details

P06/W0891Application Type: No Type (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Construction of a pond.
Location
Newington House, Newington OX10 7AG
Grid Reference
460768/196362
Applicant
Mr J D Nettleton
Newington House
Newington
WALLINGFORD
OX10 7AG
Agent
The Landscape Agency
19-23 Whitelion Street
LONDON
N1 9PD
Constraints
Grade II* Listed Building
Case Officer
Gabriella Brown
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
c/o Mrs C B Derrick
Lane End Cottage
Newington
WALLINGFORD
Oxon
OX10 7AE
21 08 2006
11 09 2006
 
Tech.Dir, Monson Engineering Ltd
21 08 2006
23 08 2006
 
County Archaeological Services
21 08 2006
08 09 2006
 
Conservation Officer
21 08 2006
11 09 2006
 
Leisure & Economic Development
21 08 2006
06 09 2006
 
English Heritage (South East)
21 08 2006
01 09 2006
 
1 Newington Cottages
Newington
WALLINGFORD
Oxon
OX10 7AG
21 08 2006
 
2 Newington Cottages
Newington
WALLINGFORD
Oxon
OX10 7AG
21 08 2006
 
Monson Engineering Ltd.
23 08 2006
05 09 2006
 
Planning Liaison Team Leader
23 08 2006
18 09 2006
 
Application Type
Minor
Application Progress
Date Received  
4th August 2006
Registration Date  
4th August 2006
Start Consultation Period  
4th August 2006
End Consultation Period  
22nd September 2006
Target Decision Date  
29th September 2006
Decision
Planning Permission on 29th September 2006
Conditions / Refusal Reasons
That the development must be begun not later than the expiration of three years beginning with the date of this permission and if this condition is not complied with this permission shall lapse. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.

That no development shall take place until a professionally competent archaeological organisation, as approved in writing by the Local Planning Authority, has been commissioned to carry out a full watching brief during the period of construction works. The watching brief shall preserve by record any archaeological features that may arise in the course of works and shall include limited archaeological excavation where necessary and the retrieval of artefact evidence. Reason: To safeguard the recording and inspection of matters of archaeological importance on the site in accordance with Policy CON11 of the adopted South Oxfordshire Local Plan.
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.