Description
Erection of replacement dwelling. Demolition of existing dwelling. (As amplified by letter from consulting engineer received on 20 July 2006 and as amended by plans accompanying letter received from the agent on 29 August 2006).
Location
Steep Hill, Cuddesdon Road Horspath OX33 1HZ
Grid Reference
458879/204259
Applicant
Mr & Mrs P Wilson
Steep Hill
Cuddesdon Road
Horspath
OXFORD
OX33 1HZ
Agent
4 G Architects
4 Nelson Street
THAME
Oxon
OX9 2DP
Case Officer
Mr A.J.Coggins
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
c/o Mrs H Kogel
63 Bowyer Road
Abingdon
Oxon
OX14 2EP
12 06 2006
06 07 2006
 
Tech.Dir, Monson Engineering Ltd
12 06 2006
14 06 2006
 
Forestry Officer
12 06 2006
21 06 2006
 
County Archaeological Services
12 06 2006
21 06 2006
 
Building Control Serv.Manager
12 06 2006
 
Environmental Health
15 06 2006
28 06 2006
 
Application Type
Other
Application Progress
Date Received  
22nd May 2006
Registration Date  
22nd May 2006
Start Consultation Period  
22nd May 2006
End Consultation Period  
5th July 2006
Target Decision Date  
17th July 2006
Decision
Planning Permission on 6th September 2006
Conditions / Refusal Reasons
That the development must be begun not later than the expiration of three years beginning with the date of this permission and if this condition is not complied with this permission shall lapse. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.

That samples of the materials to be used for the external walls and roofs shall be submitted to and approved in writing by the Local Planning Authority before any development commences. Reason: To ensure that the details of the development are satisfactory in accordance with Policy D1 of the South Oxfordshire Local Plan.

That development shall not begin until a detailed specification of the type, design and external finish of all windows and external doors has been submitted to and approved in writing by the Local Planning Authority. Reason: To ensure that the details of the development are satisfactory in accordance with Policy D1 of the South Oxfordshire Local Plan.

That before the commencement of any site works or operations relating to the development hereby permitted, an arboricultural method statement to ensure the satisfactory protection of retained trees during the construction period shall be submitted to the Local Planning Authority for approval. Written approval must be obtained prior to commencement of any site works including demolition. The matters to be encompassed within the arboricultural method statement shall include the following:- (i) A specification for the pruning of, or tree surgery to, trees to be retained in order to prevent accidental damage by construction activities; (ii) The specification of the location, materials and means of construction of temporary protective fencing and/or ground protection in the vicinity of trees to be retained, in accordance with the recommendations of BS 5837 (2005) "Trees in relation to construction", and details of the timing and duration of its erection; (iii) The definition of areas for the storage of stockpiling of materials, temporary on-site parking, site offices and huts, mixing of cement or concrete, and fuel storage; (iv) The specification of the routing and mean of installation of drainage or any underground services in the vicinity of retained trees; (v) The details and method of construction of the proposed hardstanding in the vicinity of retained trees and how these relate to existing ground levels. Reason: To protect existing trees on the site in accordance with Policy G8 of the adopted South Oxfordshire Local Plan.

That no development shall not take place until the Local Planning Authority are satisfied that contamination has been sufficiently investigated and remedial action agreed in writing. The site shall then not be occupied until any agreed action is implemented and approved by the Local Planning Authority. i. "The following measures (a-d) shall be undertaken to investigate and remediate any contamination on the site prior to commencement of the development: a) A desk study shall be submitted to and approved in writing by the Local Planning Authority. This study shall be conducted fully in line with the approach indicated in BS 10175: 2011 (Investigation of potentially contaminated sites - code of practice). The study shall include the identification of all previous site uses, potential contaminants that might reasonably be expected given those uses and other relevant information. If contamination is suspected at the site the information obtained must then be used to formulate an initial conceptual model for the site including all potential contaminant sources, pathways and receptors. b) Where contamination is identified as having the potential to be present in a) above, proposals for a site investigation to characterise the site must be submitted to and approved in writing by the Local Planning Authority. This proposal shall be designed having regard to the approved desk study and BS 10175. It should be clear about what information it seeks to obtain and how this will refine the initial conceptual model for the site. c) The approved site investigation referred to on b) above shall be fully implemented and a report submitted to the Local Planning Authority for written approval. The report shall be in line with BS 10175 and detail the works undertaken to characterise the site and contain a refined conceptual model in the light of the results of the investigation. N.B. If the Local Planning Authority is not satisfied that the site has been adequately characterised after the first stage of investigation, further works will be required to clarify any remaining uncertainties. d) Where unacceptable levels of contamination are identified, a remediation scheme shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall incorporate details of the procedures and documentation employed to validate the remediation measures identified in c) above. ii. Prior to occupation of the site, the approved remediation and validation schemes in d) above shall be fully implemented and a report submitted and approved in writing by the Local Planning Authority. Reason: To ensure that any ground and water contamination is identified and adequately addressed to ensure the safety of the development, the environment and the public and ensure that the site is suitable for the proposed use in accordance with Policy EP8 of the South Oxfordshire Local Plan.

That the existing dwelling specified in the application shall be demolished and the demolished material shall be removed from the land within three months of the first occupation of the new dwellinghouse hereby permitted. Reason: To ensure satisfactory comprehensive development in accordance with Policy G2 of the South Oxfordshire Local Plan.

That notwithstanding the provisions of Article 3 of, and Class A of Part 1 of Schedule 2 to the Town and Country Planning (General Permitted Development) Order 1995 (or any order revoking or re-enacting that Order), no extensions or alterations to the roof shall be carried out unless planning permission has first been granted by the Local Planning Authority on a formal application in respect thereof. Reason: To safeguard the character of the area and in order to protect the openness of the Green Belt in accordance with Policies G2 and GB2 of the South Oxfordshire Local Plan.

That development shall not commence on site until written approval has been granted by the Local Planning Authority to plans detailing the slab level(s) of the building(s) hereby permitted relative to existing ground level, and the development shall only proceed strictly in accordance with the details so approved. Reason: To ensure that the development is not intrusive and in accordance with Policy G2 of the South Oxfordshire Local Plan.
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.