That the development must be begun not later than the expiration of five years beginning with the date of this permission and if this condition is not complied with this permission shall lapse.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990.
Related application(s):
P09/W0963/DISThat the parking provision shall be as shown on the deposited drawing, all constructed, surfaced and laid out, thereafter retained and maintained.
Reason: To comply with the Local Planning Authority's vehicle parking standards and to protect local amenities and to comply with policies G1 and G10 of the adopted South Oxfordshire Local Plan.
Related application(s):
P09/W0963/DISThat no storage of goods shall take place other than inside the buildings.
To protect local amenities and to comply with policies G1 and C11 of the adopted South Oxfordshire Local Plan.
Related application(s):
P09/W0963/DISThat development shall not commence until details of the surface water drainage shall be submitted to and approved in writing by the Local Planning Authority.
In the interests of public health and to avoid pollution and to comply with policies G1 and G6 of the adopted South Oxfordshire Local Plan.
Related application(s):
P09/W0963/DISThat development shall not commence until details of the foul drainage shall be submitted to and approved in writing by the Local Planning Authority.
In the interests of public health and to avoid pollution and to comply with policies G1 and G6 of the adopted South Oxfordshire Local Plan.
That the rooflights in the south elevation of building B shall be conservation style which shall sit flush with the roof.
G and to comply with policies G1 and C11 of the adopted South Oxfordshire Local Plan.
That details of the barn doors shall be submitted to and approved in writing by the Local Planning Authority.
G and to comply with policies G1 and C11 of the adopted South Oxfordshire Local Plan.
No development shall take place until the LPA are satisfied that contamination has been sufficiently investigated and any remedial action approved. The site shall then not be occupied until any agreed action is implemented and approved by the Local Planning Authority.
i " the following measures ( a -d ) shall be undertaken to investigate and remediate any contamination on the site prior to commencement of the development:
a) A desk study shall be submitted to and approved in writing by the Local Planning Authority. This study shall be conducted fully in line with the approach indicated in BS10175:2001 ( Investigation of potentially contaminated sites - code of practice). The study shall include the identification of all previous site uses,potential contaminants that might reasonably be expected given those uses and other relevant information. If contamination is suspected at the site the information obtained must then be used to formulate an initial conceptual model for the site including all potential contaminant sources, pathways and receptors.
b) Where contamination is identified as having the potential to be present in a) above, proposals for a site investigation to characterise the site must be submitted to and approved in writing by the Local Planning Authority. This proposal shall be designed having regard to the approved desk study and BS 10175. It should be clear about what information it seeks to obtain and how this will refine the initial conceptual model for the site.
c) The approved site investigation referred to on b) above shall be fully implemented and a report submitted to the Local Planning Authority for written approval. The report shall be in line with BS 10175 and detail the works undertaken to characterise the site and contain a refined conceptual model in the light of the results of the investigation . NB: If the Local Planning Authority is not satisfied that the site has been adequately characterised after the first stage of investigation , further works will be required to clarify any remaining uncertainties.
d) Where unacceptable levels of contamination are identified, a remediationi scheme shall incorporate details of the procedures and documentation employed to validate the remediation measures identified in c) above.
ii) Prior to the occupation of the site, the approved remediation and validation schemes in d) above shall be fully implemented and a report submitted and approved in writing by the Local Planning Authority.
Reason
To ensure that any ground and water contamination is identified and adequately addressed to ensure the safety of the development, the environment and the public and ensure that the site is suitable for the proposed use and to comply with policies G1 and G7 of the adopted South Oxfordshire Local Plan.