Planning Application Details

P04/E0472Application Type: No Type (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Erection of replacement Bowls Pavilion.
Location
Rear of Watlington Memorial Club, High Street Watlington
Grid Reference
468948/194644
Applicant
Watlington Bowls Club
High Street
WATLINGTON
Oxon
Agent
David Beechey
"Hailands" Butts Way
Aston Rowant
Watlington
Oxon
OX49 5SZ
Constraints
Watlington Conservation Area
Case Officer
Mr T Steward
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
c/o Ms K Tynan
Watlington Parish Office
1 Old School Place
Gorwell
WATLINGTON
Oxon
OX49 5QH
13 05 2004
 
Tech.Dir, Monson Ltd
05 05 2004
 
Conservation Officer
 
Forestry Officer
 
34 Pauls Way
WATLINGTON
Oxon
OX49 5QX
 
32 Pauls Way
WATLINGTON
Oxon
OX49 5QX
 
1 Saunders Close
WATLINGTON
Oxon
OX49 5QY
 
2 Saunders Close
WATLINGTON
Oxon
OX49 5QY
28 04 2004
 
3 Saunders Close
WATLINGTON
Oxon
OX49 5QY
 
4 Saunders Close
WATLINGTON
Oxon
OX49 5QY
 
5 Saunders Close
WATLINGTON
Oxon
OX49 5QY
 
Monson Ltd
 
County Archaeological Services
26 05 2004
 
Application Type
Minor
Application Progress
Date Received  
15th April 2004
Registration Date  
19th April 2004
Start Consultation Period  
19th April 2004
End Consultation Period  
21st May 2004
Target Decision Date  
14th June 2004
Decision
Planning Permission on 4th June 2004
Conditions / Refusal Reasons
That the development must be begun not later than the expiration of five years beginning with the date of this permission and if this condition is not complied with this permission shall lapse. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990.

That, notwithstanding any indications as to those matters which may have been given in the application, no development shall take place until there has been submitted to, and approved in writing by the Local Planning Authority a full schedule of materials and finishes for the external walls and roof. Reason: To ensure that the details of the development are satisfactory in accordance with Policies G1, G8 and CON10 of the South Oxfordshire Local Plan.

Before the commencement of any site works or operations relating to the development hereby permitted, an arboricultural method statement to ensure the satisfactory protection of retained trees during the construction period shall be submitted to the Local Planning Authority for approval. Written approval must be obtained prior to commencement of any site works including demolition. The matters to be encompassed within the arboricultural method statement shall include the following:- (i) A specification for the pruning of, or tree surgery to, trees to be retained in order to prevent accidental damage by construction activities; (ii) The specification of the location, materials and means of construction of temporary protective fencing and/or ground protection in the vicinity of trees to be retained, in accordance with the recommendations of BS 5837 (1991) "Trees in relation to construction", and details of the timing and duration of its erection; (iii) The definition of areas for the storage of stockpiling of materials, temporary on-site parking, site offices and huts, mixing of cement or concrete, and fuel storage; (iv) The means of demolition of any existing site structures, and of the reinstatement of the area currently occupied thereby; (v) The specification of the routing and mean of installation of drainage or any underground services in the vicinity of retained trees; (vi) The details and method of construction of any other structures such as boundary walls in the vicinity of retained trees and how these relate to existing ground levels; (vii) The details of the materials and method of construction of the roadway, which is to be of a 'no dig' construction method in accordance with the principles of Arboricultural Practice Note 1 "Driveways close to trees", and in accordance with current industry best practice; and as appropriate for the type of roadway required in relation to its usage. (viii) Provision for the supervision of ANY works within the roof protection areas of trees to be retained, and for the monitoring of continuing compliance with the protective measures specified, by an appropriately qualified arboricultural consultant, to be appointed at the developer's expense and notified to the Local Planning Authority, prior to the commencement of development; and provision for the regular reporting of continued compliance or any departure therefrom to the Local Planning Authority. Reason: To ensure that the details of the development are satisfactory and to safeguard the beech tree in accordance with Policies G1, G8, C16 and CON10 of the South Oxfordshire Local Plan.

That all foul drainage shall be disposed of in accordance with a scheme which shall have previously been submitted to and approved in writing by the Local Planning Authority. Reason: In the interests of public health in accordance with Policy G7 of the South Oxfordshire Local Plan.
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.