Application registered
Consultation
period
Application under consideration
Decision
made
Location
Millgate, Thames Street, Sonning Eye
Grid Reference
475442/175798
Applicant
Mr A Smallman
Millgate
Thames Street
Sonning-on-Thames
Nr READING
RG4 6TW
Agent
Schofields Group Plc
Unit 44
Longshot Lane
BRACKNELL
RG42 1RL
Constraints
Sonning Eye Conservation Area
Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
Name / Number
Date Sent
Response Date
c/o Mr D R Hepburn,
Wyeval,
Kennylands Road,
Sonning Common,
READING.
RG4 9JT
02 03 2000
Tech.Dir,Babtie Engineering S.
16 02 2000
S.Clarke,Snr.Pl.Liaison Off.
30 03 2000
Mill Lodge
Sonning Eye
READING
RG4 6TW
Application Progress
Date Received
7th February 2000
Registration Date
7th February 2000
Start Consultation Period
7th February 2000
End Consultation Period
24th March 2000
Target Decision Date
3rd April 2000
Decision
Planning Permission on 3rd April 2000
Conditions / Refusal Reasons
That the development must be begun not later than the expiration of five years beginning with the date of this permission and if this condition is not complied with this permission shall lapse.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990.
That prior to the commencement of the development a schedule of materials for the construction of the conservatory shall be submitted to and approved in writing by the Local Planning Authority. Thereafter the conservatory shall not be constructed otherwise in accordance with the approved schedule of materials.
Reason: To preserve the character and appearance of the Sonning Eye Conservation Area.
That existing ground levels on the site shall not be raised.
Reason: To prevent the increased risk of flooding due to impedance of flood flows and reduction of flood storage capacity.
That no spoil or materials shall be deposited or stored on that part of the site lying within the area of land liable to flood as shown on maps held by the Environment Agency.
Reason: To prevent the increased risk of flooding due to impedance of flood flows and reduction of flood storage capacity.