The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, WA-VW-002, WA-VW-013B, WA-VW-011B, WA-VW-012B, WA-VW-001, WA-VW-014B, WA-VW-003, WA-VW-010B, WA-VW-016B and WA-VW-015B, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Except in the case of any building work hereby permitted, no change in the levels of the land shall take place unless in accordance with a detailed scheme which shall have been submitted to and approved in writing by the Local Planning Authority before any development commences on site. The scheme shall include details of existing and proposed ground levels.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Details of all boundary walls, fences and any other means of enclosure shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of any development above slab level. All such approved means of enclosure shall be erected prior to the first occupation of the development and thereafter retained as approved.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
No development above slab level shall take place until a photographic schedule of all materials to be used in the external construction and finishes of the development hereby permitted has been submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Notwithstanding the provisions of the Town and Country (General Permitted Development Order) 2015 (or any Order revoking or re-enacting that Order), no development as specified in Schedule 2, Part 1, Class A, Class C, Class D and Class E shall be undertaken without obtaining planning permission from the Local Planning Authority.
Reason: The specific circumstances of this site warrant the Local Planning Authority having control over any further development as specified in the condition to safeguard the amenities of the occupiers of the adjoining properties and the character of the area in accordance with Policies DES1, DES2 and DES6 of the South Oxfordshire Local Plan 2035.
Prior to first occupation, all carbon reduction energy efficiency measures shall be implemented in accordance with the Energy Statement hereby approved and a Verification Report shall be submitted to the Local Planning Authority and approved in writing. The Verification Report shall demonstrate (with photographic evidence) that the energy efficiency measures have been implemented. These measures shall be retained and maintained as such thereafter in accordance with the Energy Statement and Verification Report.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035.
Details of any external heating or energy generation system to be used in the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority prior to installation.
Reason: To ensure high standards of sustainable design and construction and an acceptable visual and amenity impact in accordance with Policies DES1, DES2, DES6, DES16, ENV1 and ENV12 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan WA-VW-010B and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of development, with the exception of any demolition, a full surface water drainage scheme in accordance with the surface water drainage hierarchy as set out in Part H of the Building Regulations, including details of the size, position and construction of drainage works, shall be submitted to, and approved in writing by, the Local Planning Authority. The drainage scheme shall be designed to accommodate a 1 in 100 year storm + 40% CC and shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved.
Reason: To ensure the proper provision of surface water drainage and to ensure flooding is not exacerbated in the locality in accordance with Policy EP4 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, an Electric Vehicle Charging Point shall be installed for the approved dwelling and thereafter retained as such.
Reason: To ensure sustainable forms of transport in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.