Planning Application Details

P22/S2640/OApplication Type: Outline (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Erection of detached two-storey dwelling with parking and amenity space. (As amplified by additional contamination information received 27 March 2023 and amended by revised application form removing 'layout' from the proposal and making it a reserved matter)
Location
15 Tollgate Road Culham OX14 4NE
Grid Reference
450897/195004
Applicant
Mr and Mrs M Gilbart-Smith
15 Tollgate Road
Culham
Abingdon
OX14 4NE
Agent
JCPC Ltd
5 Buttermarket
Thame
OX9 3EW
Case Officer
Paul Bowers
Telephone: 01235 422600
Email: planning@southoxon.gov.uk
View officers committee report (28/06/2023) here
Consultation / Notification
No further Representations on this application will be accepted.

Consultations / Notifications to date are shown below.

Name / Number
Date Sent
Response Date
 
Culham Parish Council
c/o Bethan Allen
46 Woodley Close
Abingdon
Oxon
OX14 1YJ
16 05 2023
09 09 2022
 
1 High Street
Culham
Abingdon
OX14 4NB
16 05 2023
18 08 2022
 
County Archaeological Services (SODC)
16 05 2023
17 05 2023
 
South and Vale Countryside Officer
30 07 2022
29 09 2022
 
Drainage - (South&Vale)
16 05 2023
26 08 2022
 
Forestry Officer (South and Vale)
16 05 2023
24 05 2023
 
South -Highways Liaison Officer (Oxfordshire County Council)
16 05 2023
08 09 2022
 
Contaminated Land
16 05 2023
22 05 2023
 
15 Tollgate Road
Culham
Abingdon
OX14 4NE
16 05 2023
 
Sage Cottage
14 Tollgate Road
Culham
Abingdon
OX14 4NE
16 05 2023
17 08 2022
 
3 High Street
Culham
16 05 2023
16 06 2023
 
via email
16 05 2023
22 08 2022
 
Application Type
Minor (Outline)
Application Progress
Date Received  
18th July 2022
Registration Date  
18th July 2022
Start Consultation Period  
29th July 2022
End Consultation Period  
19th August 2022
Target Decision Date  
30th June 2023
Target Committee Meeting  
28th June 2023
Decision
Outline Planning Permission on 30th June 2023
Conditions / Refusal Reasons
Development shall not commence until details of the reserved matters; appearance, landscaping, layout and scale have been submitted to and approved in writing by the Local Planning Authority. In the case of any reserved matter, application for approval must be made not later than the expiration of three years beginning with the date of the grant of outline planning permission. Thereafter the development shall commence not later than whichever is the later of the following dates: (a) the expiration of three years from the date of this permission; or (b) the expiration of two years from the final approval of the reserved matters, or in the case of approval on different dates, the final approval of the last such matter to be approved. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plan, P100, except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies.

Prior to the commencement of any site works or operations, including demolition and site clearance relating to the development hereby permitted, an Arboricultural Method Statement and accompanying Tree Protection Plan shall be submitted to and approved in writing by the Local Planning Authority. The Arboricultural Method Statement must include the following: (1) A specification of any pruning or tree surgery works to any trees to be retained, to prevent accidental damage by construction or demolition activities; (2) The specification and location of temporary tree protective fencing and any ground protection required to protect all retained trees in accordance with the current edition of BS 5837 ''Trees in relation to design, demolition and construction'', and details of the timing and duration of its erection; (3) The definition of areas for the storage or stockpiling of materials, temporary on-site parking, site offices and huts, mixing of cement or concrete, and fuel storage; (4) The means of demolition of any existing site structures, and of the re-instatement of the area currently occupied thereby; (5) The route and method of installation of drainage or any underground services in the vicinity of retained trees; Consideration will be made to avoid siting of utilities and service runs within the Root Protection Area (RPA) of all trees to be retained. Only where it can be demonstrated that there is no alternative location for the laying of utilities, will encroachment into the RPA be considered. Methodology for any installation works within the RPA will be provided and must be in compliance with the current edition of NJUG 'Guidelines for the planning and installation and maintenance of utility apparatus in proximity to trees'. (6) The details and method of construction of any other structures such as boundary walls in the RPA of retained trees and how these relate to existing ground levels; (7) The details of materials and method of construction of any roadway, driveway, parking, pathway or other surfacing within the RPA, which is to be of a 'No Dig' construction method, in accordance with the principles with in Arboricultural Association Guidance Note 12 "The use of cellular confinement systems near trees" and in accordance with current industry best practice; and is appropriate for the type of roadway required in relation to its usage. (8) Provision for the supervision of ANY works within the RPA of trees to be retained, and for the monitoring of continuing compliance with the protective measures specified, by an appropriately qualified arboricultural consultant, to be appointed at the developer's expense and notified to the Local Planning Authority, prior to the commencement of development; and provision for the regular reporting of continued compliance or any departure there from to the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details with the agreed measures being kept in place during the entire course of development. Reason: To safeguard trees which are visually important in accordance with Policies ENV1, DES1, and DES2 of the South Oxfordshire Local Plan 2035.

Prior to the commencement of development, with the exception of any demolition, a full surface water drainage scheme in accordance with the surface water drainage hierarchy as set out in Part H of the Building Regulations, including details of the size, position and construction of drainage works, shall be submitted to, and approved in writing by, the Local Planning Authority. The drainage scheme shall be designed to accommodate a 1 in 100 year storm + 40% CC and shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved. Reason: To ensure the proper provision of surface water drainage and to ensure flooding is not exacerbated in the locality in accordance with Policies ENV12 and EP4 of the South Oxfordshire Local Plan 2035.

That, prior to the commencement of development, with the exception of any demolition, a full foul water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall include details of the size, position and construction of the drainage scheme. Thereafter the drainage scheme shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved. Reason: To ensure the proper provision of foul water drainage and to ensure flooding and pollution is not exacerbated in the locality in accordance with policy EP4 of the South Oxfordshire Local Plan 2035.

Prior to the commencement of the development a phased risk assessment shall be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice such as Land Contamination: Risk Management 2020 and BS10175:2011 +A2:2017 'Investigation of potentially contaminated sites'. Each phase shall be submitted to and approved in writing by the Local Planning Authority. Phase 2 shall include a comprehensive intrusive investigation in order to characterise the type, nature and extent of contamination present, the risks to receptors and if significant contamination is identified to inform the remediation strategy. Phase 3 requires that a remediation strategy be submitted to and approved by the LPA to ensure the site will be rendered suitable for its proposed use. Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.

Prior to the commencement of development a detailed plan showing provision of car parking spaces to be provided within the site in accordance with the District Council's adopted car parking standards shall be submitted to and approved in writing by the Local Planning Authority and the parking spaces shall be laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles in strict accordance with the approved details prior to the first occupation of the development hereby permitted. Thereafter the car parking spaces shall be retained unobstructed except for the parking of vehicles associated with the development at all times. Reason: In the interests of highway safety and to ensure the provision of off-street car parking in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.

The development shall not be occupied until any previously approved remediation strategy has been carried out in full and a validation report confirming completion of these works has been submitted to and approved in writing by the Local Planning Authority. Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.

Prior to the first occupation of the development hereby approved, a scheme to provide an Electric Vehicle Charging Point shall be submitted to and approved in writing by the Local Planning Authority. The Electric Vehicle Charging Point shall be implemented prior to the occupation of the development and thereafter retained as such. Reason: To ensure sustainable forms of transport in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.

The developer shall confirm in writing to the Local Planning Authority the presence of any unsuspected contamination encountered during the development. In the event of any contamination to the land and/or water being encountered, no development shall continue until a programme of investigation and/or remedial works to include methods of monitoring and certification of such works undertaken. Where land contamination investigation/remedial works are required this must be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice such as Land Contamination: Risk Management 2020 and BS10175:2011 +A2:2017 'Investigation of potentially contaminated sites' and submitted to and approved in writing by the local planning authority. Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.

An Energy Statement, including SAP calculations in line with the recognised methodology set by Government, shall be submitted to the local planning authority as part of the reserved matters application. Reason: To ensure high standards of sustainable design and construction in accordance with Policy DES10 of the South Oxfordshire Local Plan 2035 and CUL9 of the Culham Neighbourhood Plan.

A Preliminary Ecological Appraisal (PEA) as informed by a suitably qualified ecologist, shall be submitted to the Local Planning Authority in support of and at the same time that any reserved matters application pertaining to this outline permission is submitted. Reason: To ensure that there is no net loss of biodiversity, in accordance with Policies ENV2 and ENV3 of the South Oxfordshire Local Plan 2035.
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.