The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, PL-02 Rev 4, PL-15 Rev 4, PL-01 Rev 4 and PL-04 Rev 4, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
No development above slab level shall take place until a photographic schedule of all materials to be used in the external construction and finishes of the development hereby permitted has been submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S2805/DISPrior to the commencement of development detailed plans showing the existing and proposed ground levels of the site together with the slab and ridge levels of the proposed development, relative to a fixed datum point on adjoining land outside of the application site, shall be submitted to and approved in writing by the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details.
Reason: In the interests of the visual appearance of the development in accordance with Policies DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S2805/DISThe cill level of the roof lights in the north elevation shall be at least 1.7 metres above the floor level of the associated rooms and shall be retained as such. No additional rooflights shall be inserted into the north elevation of the development hereby approved without planning permission from the Local Planning Authority.
Reason: To ensure that the development is not unneighbourly in accordance with Policy DES6 of the South Oxfordshire Local Plan 2035.
Prior to the construction of any development above slab level a scheme for the landscaping of the site, including the planting of live trees and shrubs, the treatment of the access road and hard standings, and the provision of retaining walls and boundary treatment shall be submitted to and approved in writing by the Local Planning Authority. These details shall include schedules of new trees and shrubs to be planted (noting species, plant sizes and numbers/densities), the identification of the existing trees and shrubs on the site to be retained (noting species, location and spread), any earth moving operations and finished levels/contours, and an implementation programme. The scheme shall be implemented prior to the first occupation or use of development and thereafter be maintained in accordance with the approved scheme. In the event of any of the trees or shrubs so planted dying or being seriously damaged or destroyed within 5 years of the completion of the development, a new tree or shrub or equivalent number of trees or shrubs, as the case may be, of a species first approved by the Local Planning Authority, shall be planted and properly maintained in a position or positions first approved in writing by the Local Planning Authority.
Reason: To help to assimilate the development into its surroundings in accordance with Policies ENV1, DES1 and DES2 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S2805/DISPrior to the commencement of development, a full surface water drainage scheme based on full infiltration unless evidenced exhausted, including details of the size, position and construction of drainage works, shall be submitted to, and approved in writing by, the Local Planning Authority. The drainage scheme shall be designed to accommodate a 1 in 100 year storm + 40% CC and shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved.
Reason: To prevent pollution and flooding in accordance with Policies ENV12 and EP4 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S2805/DISThat, prior to the commencement of development, a full foul water drainage scheme shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall include details of the size, position and construction of the drainage scheme. Thereafter the scheme shall be implemented in accordance with the approved details prior to the occupation of the development hereby approved.
Reason: To ensure the proper provision of foul water drainage and to ensure flooding and pollution is not exacerbated in the locality in accordance with policy EP4 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S2805/DISPrior to the first occupation of the development vision splays measuring 2.0 metres by 2.0 metres shall be provided to each side of the access and the vision splays shall not be obstructed by any object, structure, planting or other material with a height exceeding or growing above 0.6 metres as measured from carriageway level.
Reason: In the interest of highway safety in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan PL-04 Rev 4 and shall be constructed, laid out, surfaced, drained and completed to be compliant with sustainable drainage (SuDS) principles, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of the development a phased risk assessment shall be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice such as Land Contamination: Risk Management 2020 and BS10175:2011 +A2:2017 'Investigation of potentially contaminated sites'. Each phase shall be submitted to and approved in writing by the Local Planning Authority.
Phase 1 shall incorporate a desk study and site walk over to identify all potential contaminative uses on site, and to inform the conceptual site model. If potential contamination is identified in Phase 1 then a Phase 2 investigation shall be undertaken.
Phase 2 shall include a comprehensive intrusive investigation in order to characterise the type, nature and extent of contamination present, the risks to receptors and if significant contamination is identified to inform the remediation strategy.
Phase 3 requires that a remediation strategy be submitted to and approved by the LPA to ensure the site will be rendered suitable for its proposed use.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S2805/DISThe development shall not be occupied until any previously approved remediation strategy has been carried out in full and a validation report confirming completion of these works has been submitted to and approved in writing by the Local Planning Authority.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.
The developer shall confirm in writing to the Local Planning Authority the presence of any unsuspected contamination encountered during the development. In the event of any contamination to the land and/or water being encountered, no development shall continue until a programme of investigation and/or remedial works to include methods of monitoring and certification of such works undertaken. Where land contamination investigation/remedial works are required this must be carried out by a competent person in accordance with current government and Environment Agency Guidance and Approved Codes of Practice such as Land Contamination: Risk Management 2020 and BS10175:2011 +A2:2017 'Investigation of potentially contaminated sites' and submitted to and approved in writing by the local planning authority.
Reason: To ensure that any ground, water and associated gas contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use in accordance with Policy ENV11 of the South Oxfordshire Local Plan 2035.
The development hereby approved shall be implemented in accordance with all of the ecological mitigation and avoidance measures stated in section 4 of the supporting Ecological Appraisal (The Ecology Co-op, 21/12/2021, Ref: P5025).
Reason: To minimise the ecological impacts of development, in accordance with Policies ENV2 and ENV3 of the South Oxfordshire Local Plan 2035.
Prior to the commencement of the development above new slab level, details (including the specification, position, orientation, height, etc. as shown on plans) of the biodiversity enhancement features recommended in sections 4 and 5 of the supporting Ecological Appraisal (The Ecology Co-op, 21/12/2021, Ref: P5025) shall be submitted to and approved in writing by the local planning authority. Thereafter, the development shall be implemented in accordance with the approved details with all features provided prior to first occupation.
Reason: To secure the delivery of biodiversity enhancements on site, in accordance with Policies ENV2 and ENV3 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S2805/DISNo development shall commence unless and until a certificate confirming the agreement of an Offsetting Provider to deliver a Biodiversity Offsetting Scheme totalling a minimum of 0.88 biodiversity units has been submitted to and agreed in writing by the Local Planning Authority.
The written approval of the Council shall not be issued before the certificate has been issued by the Offset Provider. The details of biodiversity enhancements shall be documented by the Offset Provider and issued to the Council for their records.
Reason: To compensate for the net loss of biodiversity resulting from the development by providing biodiversity enhancements off site in accordance with Policy ENV3 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S2805/DISAny external lighting will only be permitted in accordance with a lighting scheme to be first submitted to and approved in writing by the Local Planning Authority. The scheme shall be designed to an E3 Environmental Management Zone as defined by the Institute of Lighting Professional Guidance for the reduction of obtrusive light and details shall include:
a) Details of all the equipment uses, specific lamps, luminaries and columns with images.
b) For each luminaire a full technical specification (e.g. wattage, colour rating)
c) Isolux diagrams overlaid over the site and adjacent areas
d) Details of lighting operation hours
Any such lighting shall be implemented in accordance with the approved details and directed downwards to prevent nuisance to adjoining residential occupiers from light spillage.
Reason: To protect the appearance of the area, the environment and wildlife, and local residents from light pollution in accordance with Policies ENV1, ENV2, ENV3 and ENV12 of the South Oxfordshire Local Plan 2035.
Related application(s):
P23/S2805/DISNotwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any Order revoking or re-enacting that Order), the enlargement, improvement or other alteration of any dwellinghouse as described in Schedule 2, Part 1, Class A and Class B of the Order shall not be undertaken without obtaining planning permission from the Local Planning Authority.
Reason: To safeguard the amenities of the occupiers of the adjoining properties and the character of the area in accordance with Policies DES1, DES2 and DES6 of the South Oxfordshire Local Plan 2035.
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any Order revoking or re-enacting that Order) the provision within the curtilage of the dwelling of any building, enclosure or swimming pool as described in Schedule 2, Part 1, Class E of the Order shall not be undertaken without obtaining planning permission from the Local Planning Authority.
Reason: To safeguard the amenities of the occupiers of the adjoining properties and the character of the area in accordance with Policies DES1, DES2 and DES6 of the South Oxfordshire Local Plan 2035.
Prior to the formation of the new access and parking area hereby approved details of the realigned steps between Henley-on-Thames public footpath 6 and Makins Recreation Ground shall be submitted to and approved in writing by the Local Planning Authority. Thereafter the realigned steps shall be constructed in accordance with the approved details prior to construction of the dwelling above slab level.
Reason: To maintain important public access through the site in accordance with Policy TRANS5 of the South Oxfordshire Local Plan 2035.