Planning Application Details

P19/S1187/FULApplication Type: Full Application (Show Map - opens in new window)
Status Bar
 
 Completed stage
 
 Current stage
 
 Next stage
Application registered
Consultation period
Application under consideration
Decision made
Description
Site Clearance works including: . Removal of trees, Landscaping, Bunds and spoil heaps; . Breaking of concrete and removal of all concrete and structures (above and below ground and); . Filling of voids; . Daylighting of water course; and . Creation of development plateaus.
Location
Land at former Didcot A Power Station Purchas Road Didcot
Grid Reference
451133/191226
Applicant
Clowes Developments (UK) Ltd
c/o Agent
Agent
Pegasus Planning Group
4 The Courtyard
Church Street
Lockington
DE74 2SL
Case Officer
No officer has yet been assigned.

The consultation process will begin once the officer has been allocated.
Application Type
Major (Full Application)
Application Progress
Date Received  
9th April 2019
Registration Date  
9th April 2019
Target Decision Date  
9th July 2019
Decision
Planning Permission on 3rd July 2019
Conditions / Refusal Reasons
The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission. Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.

That the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, S2 Rev P03, 05 Rev C, 08 Rev D, 07 Rev D, 06 Rev C, except as controlled or modified by conditions of this permission. Reason: To secure the proper planning of the area in accordance with Development Plan policies. Related application(s): P19/S2178/DIS

The development to which this permission relates shall always adhere to the dust mitigation measures outlined in the Enabling Works Air Quality Statement during construction. Reason: To protect air quality in accordance with Development Plan Policy EP1 of the South Oxfordshire Local Plan 2011.

Within 28 days of the date of this permission an updated construction Traffic Management Plan shall be submitted and approved in writing by the Local Planning Authority and development shall be carried out in accordance with the approved details at all times thereafter. Reason: In the interest of highway safety policies CSM1 & 2 of the South Oxfordshire Adopted Core Strategy 2012 and saved policies T1 & T2 of the South Oxfordshire Local Plan 2011.
Appeal
No appeal lodged.
Updates
These Planning Application Details were returned live from our back office database, and as such are as up to date as when the page was retrieved.