The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.
Reason: By virtue of Sections 91 to 95 of the Town and Country Planning Act 1990 as amended by section 51 of the Planning and Compulsory Purchase Act 2004.
Related application(s):
P14/S4114/DISThat the development hereby approved shall be carried out in accordance with the details shown on the following approved plans, 14-013-M-001, 14-013-P-005, 14-013-P-020, 14-013-P-021, 14-013-P-001A and 14-013-P-002A, except as controlled or modified by conditions of this permission.
Reason: To secure the proper planning of the area in accordance with Development Plan policies.
Related application(s):
P14/S4114/DISPrior to the commencement of the development hereby approved samples of the materials to be used for the external walls and roofs shall be submitted to and approved in writing by the Local Planning Authority.
Reason: In the interests of the visual appearance of the development in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policy G2 of the South Oxfordshire Local Plan 2011.
Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any Order revoking or re-enacting that Order), the enlargement, improvement or other alteration of any dwellinghouse as described in Schedule 2, Part 1, Class A, B and E of the Order shall not be undertaken without the prior written permission of the Local Planning Authority.
Reason: To ensure the Local Planning Authority retains control over any future development as specified in the condition in the interests of amenity and in accordance with Policy CSQ3 of the South Oxfordshire Core Strategy 2027 and Policies G2, D1 and D4 of the South Oxfordshire Local Plan 2011.
The dwellings hereby approved shall achieve Level 4 of the Code for Sustainable Homes (or any such equivalent national measure of sustainability for house design which replaces that scheme). No dwelling shall be occupied until a final Code Certificate has been issued for it certifying that Code Level 4 (or any such equivalent national measure of sustainability for house design which replaces that scheme) has been achieved.
Reason: To ensure high standards of sustainable design and construction in accordance with Policy CSQ2 of the South Oxfordshire Core Strategy 2027.
Prior to the first occupation of the development hereby approved, the parking and turning areas shall be provided in accordance with the approved plan 14-013-P-005 and shall be constructed, laid out, surfaced, drained and completed, and shall be retained unobstructed except for the parking of vehicles associated with the development at all times.
Reason: In the interests of highway safety and in accordance with Policies T1 and T2 of the South Oxfordshire Local Plan 2011.
No surface water from the development shall be discharged onto the adjoining highway
Reason: In the interests of highway safety in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.
A Construction Traffic Management Plan (CTMP) shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The approved CTMP shall be implemented prior to any works being carried out on site, and shall be maintained throughout the course of the development.
Reason: In the interests of highway safety and to mitigate the impact of construction vehicles on the surrounding highway network, road infrastructure and local residents, particularly at morning and afternoon peak traffic times and in accordance with Policy T1 of the South Oxfordshire Local Plan 2011.